Ambient Air Monitoring Program Section No. 4
Quality Assurance Project Plan Revision No.: 0
130 Liberty Street - NY, NY Date: August 2005
Lower Manhattan Development Corporation Page 11 of 116
review, and submit the revised QAPP to EPA for review and approval. After the revised QAPP
has been approved, the revised QAPP will be provided to the team members, according to the
original QAPP Distribution List. The prior QAPP will be removed and deemed obsolete; copies
of the prior QAPP will be retained in project files for documentation purposes.
4.3 Personnel Responsibilities and Qualifications
The responsibilities of management, QA, field, and laboratory personnel are outlined below.
4.3.1 Management Responsibilities
EPA Project Manager
The U.S. EPA Project Manager for the 130 Liberty Street Ambient Air Monitoring Program is
Mr. Pat Evangelista. His primary responsibilities include administration of EPA responsibilities,
oversight of the day-to-day activities, and receipt of all required written matter. Mr. Evangelista
is also responsible for providing technical oversight and guidance and reviewing all technical
deliverables, including plans and reports.
TRC Piincipal-in-Charge
The TRC Principal-in-Charge, Mr. Edward Gerdts, will be responsible for periodically auditing
the program to ensure compliance with TRC’s standard management procedures and providing
all necessary senior technical support and program planning.
TRC Project Manager
The TRC Project Manager, Mr. Gary Hunt, has responsibility for technical and scheduling
matters and will serve as the main contact with the LMDC and EPA Project Manager. Other
duties, as necessary, include
• Assuring adherence to project plans and obtaining approvals for any changes to these plans,
• Assuring that approved procedures meet project objectives,
• Reviewing and approving all sampling procedures,
• Assigning duties to project staff and orienting the staff to the specific needs and requirements
of the project,
• Serving as the focus for coordination of all field task activities, communications, reports, and
technical reviews, and other support functions, and facilitating activities with the technical
requirements of the project,
• Coordinating field and office activities with the TRC Project QA Officer and TRC Eield
Sampling Coordinator,
• Implementing recommendations made by the TRC Project QA Officer,
L2005-346 Rev. 1
CITY_DEP_WORBY_CANNATA_SUBP_000114652
NYC-WTC_000428335