NYC Law Department release
Independent mirror · updated as the City releases more · v1.5.1
☕ Buy me a coffee
← Document results/Unboxed/No folder label
Document / 2 pages

Asbestos exceedance event, AFD Exhaust, 2005

Machine-extracted title · confidence 32%

Event summary of March 14, 2005 asbestos fiber exceedance and notification.

NYC-WTC_000426554–000426555
Page image
Scanned page image, NYC-WTC_000426554
OCR text

OCR status: ok · source: pdftotext

NYC 9/11 Public Portal Document

RJ LeeGroM/?, Inc. Exceedance Report Date of Exceedance: March 14, 2005 Analyte: Airborne Asbestos Location: (South) AFD Exhaust. Carlisle Street Sidewalk Bridge Concentration: 88.2 s/niiii’ Trigger Level: 70 s/mm^

Summary of Event:

On Monday, March 14, 2005 sampling for airborne asbestos fibers was conducted at the (South) AFD Exhaust on the Carlisle Street Sidewalk Bridge location. The sampling was initiated at 14:47PM on March 14, 2005 and concluded at 22:47PM that same day (total collection time: 480 min.; sample volume: 2400 liters). The sample was received at the RJ Lee Group laboratory (Monroeville, PA) on Wednesday, March 16 and analyzed that evening using the AHERA TEM method. The results from the analysis of the sample reported an asbestos fiber concentration of 88.2 s/mmC

The exceedance was reported by the laboratory via telephone to Mike Campbell on Wednesday night and the results were e-mailed to all parties immediately. The DEP and EPA were notified, via telephone, of the exceedance today, Thursday morning and a conference call to discuss this exceedance was held at 12:30PM this afternoon.

Corrective Action:

The AFD that had the exceedance was located on the Sth floor. During the 2“* shift on Monday, March 14, the shift of the exceedance, there was no work performed on this floor other than regular filter maintenance of the AFD’s.

Upon receipt of the exceedance this AFD was immediately shut down, the intake was sealed with poly and the slinky hose was taped shut and the spare AFD on the 8* floor was initialized. Since all abatement and final cleaning activities had previously been completed on this floor and encapsulation of the floor had taken place only hours before the report of the exceedance, there was no work stoppage.

Subsequent investigation of the exceedance included, a visual inspection of the AFD, a review of PAL’s (the abatement contractor) site log along witli interviews of the site management team. Visual inspection of the AFD showed taped repairs and a stretched, uncoiled, section of the “slinky” exhaust hose, also the HEPA filter appeared to be seated properly. The PAL site log did not have any information regarding this AFD, during the shift in question, however PAL representatives stated that during regular filter maintenance a breech in the “slinky” hose was found and a repair, utilizing spray glue and duct tape was performed. This repair reportedly required the AFD to be shut down for approximately 10 minutes.

No definite cause of the exceedance has been identified other than the reference to the slinky hose repair, reported to have occurred during the sampling time frame of this exceedance.

Attachments:

Report summary -AHERA TEM Air Results for March 14, 2005

Submitted By: Mike Campbell Date: March 17, 2005 Draft

CITY_DEP_WORBY_CANNATA_SUBP_000091875

NYC-WTC_000426554

OCR can misread numbers and units. Confirm readings against the page image before using them.

NYC-WTC_000426554Source: NYC Law Department, mirrored locally

Related records

Browse subjects →

Ranked by indexed similarity. Reasons describe shared subjects and filing context; check the source records.

Same-box records

Filed elsewhere

No available related records indexed in this group.

More like this page

Similar subjects in other documents. Similarity does not establish the same event, measurement or conclusion.

Others also read

Readers open these alongside this record — through an Ask answer, the same folder, or indexed similarity. Not a claim they are about the same event.

NYC-WTC_000424853

Exceedance report for airborne asbestos (TEM AHERA) with 88.2 fibers/mm3; notification to DEP/EPA, Mar 2005.

Similar indexed content

NYC-WTC_000427348

Summary of March 5, 2005 airborne asbestos sampling at northwest location.

Similar indexed content

Compare copies and versions →