QA plan for ambient air monitoring program for LMDC deconstruction at 130 Liberty Street.
79 shared non-person entities · 1 shared topics · similarity 1.000
machine-extracted · confidence unavailable · Check page ↗Quality assurance plan and project details for ambient air monitoring near 130 Liberty Street, Sep 2005.
NYC-WTC_000423219–000423350OCR status: ok · source: pdftotext
NYC 9/11 Public Portal Document
Ambient Air Monitoring Program Section No. 7 Quality Assurance Project Plan Revision No.: 0 130 Liberty Street - NY, NY Date: September 7, 2005 Lower Manhattan Development Corporation Page 30 of 124
7.1.1 Sampling Tasks
Sampling phases will consist of the following segments: Background, Phase I - Preparation Phase and Phase I - Asbestos and COPC Abatement, and Phase II - Structural Deconstruction. General descriptions of the work included in each phase are presented in the Ambient Air Monitoring Program for the 130 Liberty Street Deconstruction Project, August 2005. Sampling methods, sampling QC, sample handling and custody are discussed in other sections of this QAPP. Tables 7-la, 7-lb, and 7-lc provide a general summary of target parameters, and numbers of field samples and QC samples expected to be collected on a weekly basis for each phase of the program. Tables 7-2 and 7-3 provide a summary of sampling frequencies after the background phase has been completed. Sampling locations are noted on Figures 7-1 and 7-2. Table 7-4 summarizes the sampling locations and the expected use of the data at each location. Photographs of each site are included in Attachment A.
Background
The background ambient air sampling period will consist of two weeks (14 consecutive calendar days) of monitoring performed immediately prior to the start of Phase I - Preparation Phase activities. Samples will be collected at five (5) stations (4 ground level and 1 roof top location located on the roof of the fire house [FDNY 10-10 House]) in the monitoring network. All target parameters will be collected over a 24-hour integrated period with the exception of asbestos, silica, PMio, PM2.5, and mercury. Mercury will be monitored utilizing a direct read mercury analyzer. PM , and PM; will be monitored continuously at each of the five (5) sites while asbestos and silica measurements will be taken at a frequency of once per work shift at each of the sites.
Phase I: Preparation and Asbestos and COPC Abatement and Removal
During the Phase I (abatement phase) air monitoring will take place at twelve (12) stations each day. During the first three (3) days only of Phase I Abatement work, samples will be collected and analyzed for semivolatile organics to include PCDDs/PCDFs, PAHs and PCBs. After this first three (3) day period, sampling for semivolatile organics will be reduced to a once per week frequency employing the entire station network. One day per week on a rotating basis (week #1 Monday, week #2 Tuesday, etc.) samples will be collected at every station in the network. The schedule will be repeated until project completion.
The semivolatile organic samples collected employing this weekly sampling frequency will not be processed for analyses; rather they will be placed in archival storage at the laboratory. A single set of samples will be selected from each weekly sampling event to undergo analyses for PCDDs/PCDs, PAHs and PCBs. The station with the highest 24-hour average PMio concentration (pg/m^) recorded with a collocated organic sample each week will be selected for semivolatile organic analyses.
CITY_DEP_WORBY_CANNATA_SUBP_000058218
NYC-WTC_000423249
OCR can misread numbers and units. Confirm readings against the page image before using them.
Ranked by indexed similarity. Reasons describe shared subjects and filing context; check the source records.
NYC-WTC_000422676
QA plan for ambient air monitoring program for LMDC deconstruction at 130 Liberty Street.
79 shared non-person entities · 1 shared topics · similarity 1.000
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000426821
QA plan reference for deconstruction ambient air monitoring, Sept 2005.
79 shared non-person entities · 1 shared topics · similarity 1.000
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000421972
QA plan for ambient air monitoring for the 130 Liberty Street deconstruction project, Sept 2005.
79 shared non-person entities · 1 shared topics · similarity 1.000
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000426556
Quality assurance plan for ambient air monitoring, 130 Liberty Street, Sept 2005.
79 shared non-person entities · 1 shared topics · similarity 1.000
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000421711
Quality assurance plan for ambient air monitoring during LMDC project at 130 Liberty Street.
77 shared non-person entities · 1 shared topics · similarity 1.000
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000421577
QA plan for ambient air monitoring for the 130 Liberty Street deconstruction project, Sept 2005.
75 shared non-person entities · 1 shared topics · similarity 0.999
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000427221
Draft QA Project Plan for ambient air monitoring at 130 Liberty Street deconstruction, TRC scope, Aug 2005.
72 shared non-person entities · 1 shared topics · similarity 0.999
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000447031
QA plan document for ambient air monitoring program for Liberty Street deconstruction.
79 shared non-person entities · 1 shared topics · similarity 0.999
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000443239
QA plan for ambient air monitoring at 130 Liberty Street deconstruction project, LMDC.
79 shared non-person entities · 1 shared topics · similarity 0.999
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000447891
QA plan for ambient air monitoring at 130 Liberty Street, Sept 7, 2005.
79 shared non-person entities · 1 shared topics · similarity 0.998
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000449908
QA plan for ambient air monitoring at 130 Liberty Street deconstruction project, Sept 7, 2005.
79 shared non-person entities · 1 shared topics · similarity 0.998
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000448520
Quality assurance plan for ambient air monitoring during deconstruction at Liberty Street.
79 shared non-person entities · 1 shared topics · similarity 0.998
machine-extracted · confidence unavailable · Check page ↗No available related records indexed in this group.
Similar subjects in other documents. Similarity does not establish the same event, measurement or conclusion.
NYC-WTC_000422676
QA plan for ambient air monitoring program for LMDC deconstruction at 130 Liberty Street.
Similarity score 1.000 (not a probability)
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000426556
Quality assurance plan for ambient air monitoring, 130 Liberty Street, Sept 2005.
Similarity score 1.000 (not a probability)
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000421972
QA plan for ambient air monitoring for the 130 Liberty Street deconstruction project, Sept 2005.
Similarity score 1.000 (not a probability)
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000421711
Quality assurance plan for ambient air monitoring during LMDC project at 130 Liberty Street.
Similarity score 1.000 (not a probability)
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000426821
QA plan reference for deconstruction ambient air monitoring, Sept 2005.
Similarity score 0.999 (not a probability)
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000421577
QA plan for ambient air monitoring for the 130 Liberty Street deconstruction project, Sept 2005.
Similarity score 0.998 (not a probability)
machine-extracted · confidence unavailable · Check page ↗Machine-extracted building matches; verify each source. Buildings, never households.
Readers open these alongside this record — through an Ask answer, the same folder, or indexed similarity. Not a claim they are about the same event.
QA plan for ambient air monitoring program for LMDC deconstruction at 130 Liberty Street.
Similar indexed content
QA plan reference for deconstruction ambient air monitoring, Sept 2005.
Similar indexed content
QA plan for ambient air monitoring for the 130 Liberty Street deconstruction project, Sept 2005.
Similar indexed content
Quality assurance plan for ambient air monitoring, 130 Liberty Street, Sept 2005.