Daily work force report, World Trade Center, Jan 22, 2002

Machine-extracted title · confidence 28%

Night final daily workforce at World Trade Center site, Jan 22, 2002.

NYC-WTC_000419155
Page image
Page image not rendered yet.
The pipeline renders page images incrementally; check back or read the OCR text alongside.
OCR text

OCR status: ok · source: pdftotext

NYC 9/11 Public Portal Document

GRACE CONTRACTING CORP. 161-45 esi Road, WnilMtOO», N.Y. 11357.(716)767-6000 DATE; 1/22/02 NIGHT FINAL

DAILY WORK FORCE REPORT

Job Nam* & Location; World Trade Center Contract No. Weather Conditions ______ ___

Labor Equipment =aiKK CLASSIFICATION QUANT. ] Description superintendent I CAT 966 LOADER_______ 1 PROJECT ENGINEER 1 l|CAT 973 LOADER 1 OFFICE ENGINEER I CAT 365 GRAPPLER 2 FOREMEN___________ 1 [cat 375 GRAPPLER 1 SAFETY OFFICER CAT 375 GRAPPLER 1 laborers________ 9 HITACHI 750 GRAPPLER 1 IRON WORKERS HITACHI 550 GRAPPLER 1 LOCAL 14________ HITACH11200 GRAPPLER 1 LOCAL 15________ 6 185 CFM COMPRESSOR 1 CARPENTER _ 235 HAMMER HOE RAM •MANNED BY TULLY CARPENTER FOREMAN _ MECHANICS TRUCK 1 1 TEAMSTERS (FUEL) 2 _ TOOLTRUCK________ MECHANICS_________ 2 TOOL VAN_________ HOUSE WRECKERS 2 2 ROLL OFF ________ DUMP TRAILERS 8 _ YUKES _________ _ 4 HIGH DECK TRAILERS 2 " WELDING TRUCK DELIVERIES; FUEL TRUCK 1 PICKUP TRUCKS 3 LIGHT TOWERS 5 SITE MULE 2 ’NOTE; wrc TRUCKING 14 DRIVERS “ DUMP TRUCKS |[l0 WHEEL DUMP TRUCiT" "[FLASHING ARROW BOARD OFFICE TRAILER/GENER. 1 . DELAYS; TRUCK 62 WAS DELAYED FOR 2.5 HOURS CARGO BOXES 4 DUE TO BRAKE PROBLEMS FLAT TRUCK 1 PUMP 2 RAINMAKER/GENIE LIFT •235 MANNED BY TULLY FROM 5PM-12AM

Description of Work; COMPLETED WORK CONTINUED REMOVING DEBRIS FROM LOWER LEVELS OF TOWER TWO TO ACCOMODATE BRIDGE MAINTAINED TRAFFIC FLOW INTO AND OUT OF AREA______________________________________________ TRUCKS TO PIER 6 DELAYED APPROXIMATELY 1 HOUR BY DOT AND ConEd WORK ON TUNNEL AND ROAD Loads OUT; 117 YUKESOUT: 120

GRACE CONTRACTING CORP Approved By; BY; Cl!®!— For; SUPERINTENDENT 01.603693

CITY_2IMCl0 0_0 010 7 3 4 6 4 NYC-WTC_000419155

OCR can misread numbers and units. Confirm readings against the page image before using them.

NYC-WTC_000419155Source: NYC Law Department, mirrored locally

Related records

Browse subjects →

Ranked by indexed similarity. Reasons describe shared subjects and filing context; check the source records.

Same-box records

Filed elsewhere

No available related records indexed in this group.

More like this page

Similar subjects in other documents. Similarity does not establish the same event, measurement or conclusion.

Others also read

Readers open these alongside this record — through an Ask answer, the same folder, or indexed similarity. Not a claim they are about the same event.

Compare copies and versions →