Asbestos Abatement
4. A static negative air pressure of 0.02 inches (minimum) water column
shall be maintained at all times in the work place during abatement to ensure
that contaminated air in the Work Area does not filter back to uncontaminated
areas.
5. On loss of negative pressure or electric power to the negative pressure
ventilating units, abatement shall stop immediately and shall not resume until
power is restored and negative pressure ventilation equipment is operating
again.
6. Negative pressure ventilation equipment shall be exhausted to the outside
of the building away from occupied areas.
a. At no time shall the negative pressure ventilation unit exhaust with
40 feet of a receptor or adversely affect the intake ports, louvers, or
entrances for the building or adjacent buildings.
b. Heavy duty ducting of equivalent, or larger, shape and dimension
as that of the negative pressure ventilation exhaust port shall be
used to exhaust to the structure.
c. All ducting shall be sealed and braced or supported to maintain
airtight joints.
7. Where ducting to the outside is not possible, a second negative pressure
ventilation unit compatible with the primary unit's capacity shall be
connected in series. The area receiving the exhaust shall have sufficient, non
recycling exhaust capacity to the outside of the structure.
8. In the event that there is a failure of the containment system or a breech in
the Isolation Barriers, all abatement work will cease and the Contractor will
immediately correct the condition. Abatement work will not resume until the
Work Area has been smoke tested by the third party laboratory and approved
by the Construction Manager.
F. LOCKDOWN ENCAPSULATION PROCEDURES
The following procedures shall be followed to seal in nonvisible residue while
conducting lockdown encapsulation on all surfaces from which ACM is removed:
a. Only encapsulants rated as acceptable or marginally acceptable on
the basis of Battelle Columbus Laboratory test procedures and
rating requirements developed under the 1978 USEPA Contract
shall be used for lockdown encapsulation.
CAPITAL PROJECT NUMBER PO79201K 02081-21
100: CONTRACT DOCUMENTS REV. May 3,2000
-21 -100% CONTRACT DOCUMENTS
REV. 0: DATE