GRACE CONTRACTING CORP. 151-45 Sih Road. Whitestone. N.Y. 11357- (718) 767-9000 DATE: 1-7-02 DAY FINAL
DAILY WORK FORCE REPORT
Job Name & Location: World Trade Center Contract No. Weather Conditions
Labor Equipment CLASSIFICATION QUANT. Description [MANNED STANDBY IDLE [SUPERINTENDENT 1 IICAT 966 LOADER 1 PROJECT ENGINEER CAT 446 BACKHOE 1 OFFICE ENGINEER I CAT 973 LOADER 1 FOREMEN 1 CAT 365 GRAPPLER 1 SAFETY OFFICER 1 CAT 375 BUCKET 1 LABORERS 21 CAT 375 GRAPPLER 1 [IRON WORKERS HITACHI 750 GRAPPLER 1 LOCAL 14 6 HITACHI 550 BUCKET 1 LOCAL 15 9 HITACH11200 GRAPPLER 1 CARPENTER 185 CFM COMPRESSOR 1 CARPENTER FOREMAN 235 HAMMER HOE RAM 1 TEAMSTERS 1 MECHANICS TRUCK 2 MECHANICS 3 TOOL TRUCK HOUSE WRECKERS 4 TOOL VAN 1 ROLL OFF DUMP TRAILERS LOW BED TRAILER DELIVERIES:__________________________________ HIGH DECK TRAILERS GREAT BEAR - 8 FIVE GALLON BOTTLES OF WATER WELDING TRUCK 1 AWISCO - 24 REFLECTIVE SAFETY VESTS FUEL TRUCK 1 PICKUP TRUCKS 5 LIGHT TOWERS 13 SITE MULE 3 DUMP TRUCKS 10 WHEEL DUMP TRUCK FLASHING ARROW SOARD 1 OFFICE TRAILER/GENER. 1 CARGO BOXES 3 FLAT TRUCK PUMP 2 RAINMAKER/GENIE LIFT 1
Description of Work:____________________________________________________________________________ COMPLETED WORK___________________________________________________________________________ CONTINUE REMOVING DEBRIS FROM LOWER LEVELS OF TOWER 2 AND SOUTH OF MAIN CHILLER PLANT MAINTAIN TRAFFIC FLOW INTO AND OUT OF AREA _____________________________________________ MAN WATERING STATIONS FOR DUST CONTROL_________________________________________________ LOADS OUT: 142___________________________________________________ ____________________ EUKES OUT: 226
GRACE CONTRACTING CORP| Approved By: BY: Title:_______ For: SUPERINTEND^
DAILY WORK FORCE REPORT0107D.XLT
CITY_21MC100_011874097
NYC-WTC_000407887
OCR can misread numbers and units. Confirm readings against the page image before using them.
Ranked by indexed similarity. Reasons describe shared subjects and filing context; check the source records.
NYC-WTC_000342291
Nightly daily workforce report for World Trade Center construction.
2 shared non-person entities · 1 shared topics · similarity 0.993
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000237643
Day shift report from Grace Contracting documenting labor and equipment counts at the World Trade Center site on January 9, 2002.
2 shared non-person entities · 1 shared topics · similarity 0.993
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000263614
Daily workforce and equipment roster for World Trade Center site, Jan 2002.
2 shared non-person entities · 1 shared topics · similarity 0.992
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000342294
Day shift daily workforce report with personnel and machinery.
2 shared non-person entities · 1 shared topics · similarity 0.992
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000235137
Day shift daily log of laborers and heavy equipment at the World Trade Center site on January 7, 2002.
2 shared non-person entities · 1 shared topics · similarity 0.992
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000237641
Day shift report from Grace Contracting documenting labor and equipment counts at the World Trade Center site on January 8, 2002.
2 shared non-person entities · 1 shared topics · similarity 0.992
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000429383
Day shift roster and equipment details for World Trade site, Jan 2002.
2 shared non-person entities · 1 shared topics · similarity 0.992
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000342296
Day shift daily workforce report listing crew and equipment.
2 shared non-person entities · 1 shared topics · similarity 0.992
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000341037
Night shift worker and equipment tally for World Trade Center project.
2 shared non-person entities · 1 shared topics · similarity 0.992
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000305343
Night preliminary daily workforce log for World Trade Center site, Dec 2001.
2 shared non-person entities · 1 shared topics · similarity 0.992
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000342292
Day shift daily workforce report detailing labor and equipment.
2 shared non-person entities · 1 shared topics · similarity 0.992
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000322155
Day final daily workforce and equipment for World Trade Center site, January 15, 2002.
2 shared non-person entities · 1 shared topics · similarity 0.991
machine-extracted · confidence unavailable · Check page ↗No available related records indexed in this group.
Similar subjects in other documents. Similarity does not establish the same event, measurement or conclusion.
NYC-WTC_000342291
Nightly daily workforce report for World Trade Center construction.
Similarity score 0.996 (not a probability)
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000237643
Day shift report from Grace Contracting documenting labor and equipment counts at the World Trade Center site on January 9, 2002.
Similarity score 0.996 (not a probability)
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000263614
Daily workforce and equipment roster for World Trade Center site, Jan 2002.
Similarity score 0.996 (not a probability)
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000342294
Day shift daily workforce report with personnel and machinery.
Similarity score 0.996 (not a probability)
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000235137
Day shift daily log of laborers and heavy equipment at the World Trade Center site on January 7, 2002.
Similarity score 0.996 (not a probability)
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000237641
Day shift report from Grace Contracting documenting labor and equipment counts at the World Trade Center site on January 8, 2002.
Similarity score 0.996 (not a probability)
machine-extracted · confidence unavailable · Check page ↗Readers open these alongside this record — through an Ask answer, the same folder, or indexed similarity. Not a claim they are about the same event.
NYC-WTC_000342291
Nightly daily workforce report for World Trade Center construction.
Similar indexed content
Day shift report from Grace Contracting documenting labor and equipment counts at the World Trade Center site on January 9, 2002.
Similar indexed content
NYC-WTC_000263614
Daily workforce and equipment roster for World Trade Center site, Jan 2002.
Similar indexed content
NYC-WTC_000342294
Day shift daily workforce report with personnel and machinery.
Similar indexed content
NYC-WTC_000235137
Day shift daily log of laborers and heavy equipment at the World Trade Center site on January 7, 2002.
Similar indexed content