NYC Law Department release
Independent mirror · updated as the City releases more · v1.5.1
☕ Buy me a coffee
← Document results/Unboxed/No folder label
Document / 1 page

WTC surveillance observation report, Apr 4 2002

Machine-extracted title · confidence 28%

Observations and hazard notes from WTC site monitoring on Apr 4, 2002.

NYC-WTC_000388722
Page image
Page image not rendered yet.
The pipeline renders page images incrementally; check back or read the OCR text alongside.
OCR text

OCR status: ok · source: pdftotext

NYC 9/11 Public Portal Document

WTC Daily Safety Report 4 Apr-02 UhcrtY Report Period 24 hours besinnlng 7 W AH on M 11 ill

Obeervatlon/Hazard and Location Grid Contractor Corrective Action Required Person Resoonsa Contacted Hole in WTC 6 B2 near north slurry wall is partially K 3 L 3 Tully Hole needs to be covered with a sheet of plywood Open Need to discuss with dayshift to have carpentry crew uncovered____________________________ _ make needed changes The wooden ramp to the PATH tracks has a 3 opening H 8 Bovis/Amec Guardrail and midrail need to be Installed Open adjacent to the handrails at the top of the ramp noithside

Panel box for storage area temporary llghbng without a T7 Bovis/Amec Provide lock for electrical box .rMbHdfcaalar^ Open lock adjacent to stairwell______________________ Kefueling pump in pit for excavating equipment without L7 Tully Provide exUnguisher provide diesel fuel placard and Charlie Keeling Open extinguisher or placarding and warnings____________ flammable labeling No caution signs High Voltage at Safeway asbestos J 12 Bovis/Amec Provide proper electrical labels and boxes need to be Open removal area between wooden shed and blue tarping In checked for GFCI protection along with lockage CM git______________________________________ Live electrical equipment In WTC 5_______________ P-4 Tully Identify live equipment and de-energize KsffivMBielev^ Open Compressed gas cylinders stored in confined space area M 2 M 3 Tully Gas cylinders need to stored outside of confined Foreman Open WTC6 Levels____________________________ space area Fall Protection No barriers along west edge of tieback P15 Bovis/Amec Install barriers along west edge of bench Scott/Rocco ^pen will install barriers morning of April 5 2002 bench (debris pile) Compressed air hoses In JI staircase landings of WTC 8 WTC 6 Nicholson Relocate compressed air lines Don Pendelton Open creating fall hazard__________________________ Damaged metal railing In stairway leading to below grade R-4 EROC Metal railing badly damaged Potential tall hazard BUI Ryan Open areas of WTC 5 needs to be repaired/replaced_______ Repair and/or replace railing PPE use by Mechanics all areas(Service truck V 106 0 10 R e Tully Enforce use of hardhats and safety glasses by Carlos Ed Segall Open Bobcat and Hitachi mechanics) mechanics Fall Protection open floor holes_________________ MO Component Install secured, labeled covers______________ OgOT Fall hazards around trenches on Liberty St P17 Tully Re-bistall orange safety fence when work Is not Charlie Keeling Open ongoing Oxygen and Acetylene cylinders stored adjacent to oil M-11 Tully Store all cylinders 2S feet from stored oil containers Charlie Keeling Open storage In pit Stairwell leading under WTC S no longer has restricted 03 Tully Barricades need to be piece to prevent access to Charlie Keeling Open access levels below Storage of numerous Oli cqna gas cans compressed gas PIT AREAS cylinders Inside pit In unsafe manner Bovis/Amec Designate storage area and store material as per fire department bulletin #9 (1/30/2002) Ray Master Ongoing Addressed at Supervisors 8 OOam meeting on 4-3-02 ICM Electrical storage shed in pit without lockable door or "high Pie Moretrench Provide lockable door and proper signage for shed n progress List was made and SJ electric will be taking actions /V\ I I II ni^iiifiiaI voltage signage____________________________ to complete___________________________________ Electrical Hazard Open electrical boxes throughout WTC h3 J3 SJ Electrical Screw covers onto all electrical boxes ^JeOMStafctiak. In progress List was made and SJ electric will be taking actions 8 Wiring is taped but covers are not secured to boxes to complete

Electrical missing light cages throughout WTC 6 1-3 K-3 SJ Electrical Secure cages on all lights In progress List wes made and SJ electric will be taking acUons to complete No GFCI Protection for temporary lighting In WTC floors B- l-3toM-3 S J Electrical Plan Is to install GFCI circuit breakers on Temp Afnastatcbek, in progress List was made and SJ electric will be taking actions ltoB-4 power circuits B-1 level Circuit Panel from ®41 Amp to complete RPL LO78 generator o Extenalon cord at generator by bum station on haul road S-6 EROC Provide longer extension cord and provide a BillffpSM ’57?™ IT progress Bum station workers Instructed not to unplug fans used for fans for air moving in WTC 6 being unplugged temporary power branch circuit for WTC S Utosatsy Temporary power to ba supplied to below grade areas of WTC l"^ ho Fall Protection Wire rope cables Installed on Jersey sue Wide Bovis/Amec Modify cables per engineered drawings and ensure JeffTasea Jeff In Progress Component has ordered the necessary hardware

s o barriers as fall arrest anchors should be modified per LZA Several wooden barricades used on crane deck In pit are broke____________________________________ M-e Component proper tie-off practices

Repair or replace barricades Melofchek, T for the required changes

Open Building e Level B 3 tie-back operators not wearing Ray Master/Jeff respirators________________________________ J3 OHnhnmn Enforce use of PPE Melofchek Open o Southwest slair tower needs ramp Into pit K16 Tully Install ramp Into pH Sam/Foreman Open co Cti co Cti

NYC-WTC_000388722

OCR can misread numbers and units. Confirm readings against the page image before using them.

NYC-WTC_000388722Source: NYC Law Department, mirrored locally

Related records

Browse subjects →

Ranked by indexed similarity. Reasons describe shared subjects and filing context; check the source records.

Same-box records

Filed elsewhere

WTC Daily Site Evaluation, Oct 23, 2001 · Box unavailable

NYC-WTC_000204854

Daily environmental, safety, and health evaluation log for the World Trade Center site dated October 23, 2001, noting PPE usage, fall protection, and structural cracks.

2 shared non-person entities · 1 shared topics · similarity 0.908

machine-extracted · confidence unavailable · Check page ↗

More like this page

Similar subjects in other documents. Similarity does not establish the same event, measurement or conclusion.

WTC Daily Site Evaluation, Oct 23, 2001 · page 1

NYC-WTC_000204854

Daily environmental, safety, and health evaluation log for the World Trade Center site dated October 23, 2001, noting PPE usage, fall protection, and structural cracks.

Similarity score 0.953 (not a probability)

machine-extracted · confidence unavailable · Check page ↗

Others also read

Readers open these alongside this record — through an Ask answer, the same folder, or indexed similarity. Not a claim they are about the same event.

NYC-WTC_000407564

Daily site safety evaluation noting PPE, elevated hazards, and structural concerns at WTC sites; safety recommendations.

Similar indexed content

NYC-WTC_000187868

Daily environmental safety evaluation report for the WTC site noting PPE issues, fall protection gaps, and structural cracks.

Similar indexed content

NYC-WTC_000360441

WTC site safety evaluation with PPE, fall protection, and crane concerns discussed.

Similar indexed content

NYC-WTC_000302137

Daily safety evaluation listing issues at WTC sites AMEC and AMEX for action.

Similar indexed content

Compare copies and versions →