a GRACE CONTRACTING CORP. 11.4S 6th Road. WhileslonB, N.y. 11357-(718) 767-9000
DAILY WORK FORCE REPORT DATE; MONDAY 12/3/01 NIGHT (FINAL)
Job Name & Location: World Trade Center Contract No. Weather Conditions CLEAR & COOL
~ i Labor , CLASSIFICATION QUANT. Description Equipment IMANNEO STANDBY dleI M SUPERINTENDENT i 2 CAT 966 LOADER 1 PROJECT ENGINEER : 1 CAT 446 BACKHOE 1 OFFICE ENGINEER CAT 973 LOADER 1 FOREMEN 1 CAT 365 GRAPPLER 1 SAFETY OFFICER CAT 375 GRAPPLER 1 LABORERS 16 HITACHI 750 GRAPPLER 1 IRONWORKERS HITACHI 550 BACKHOE 1 LOCAL 14 5 HITACHI 550 GRAPPLER '1 LOCAL 15 8 HITACHI 1200 GRAPPLER 1 CARPENTER 185 CFM COMPRESSOR 1 CARPENTER FOREMAN 235 HAMMER HOE RAM TEAMSTERS 11 MECHANICS TRUCK 1 1 MECHANICS 1 TOOL TRUCK HOUSE WRECKERS 7 TOOLVAN ROLL OFF DUMP TRAILERS 7 LOW BED TRAILER • UG INTO VISTA FROM EAST WITH 1200 - LOADED EUKES HIGH DECK TRAILERS 3 WELDING TRUCK '■ |375 DUG PARALLEL TQ WEST SIDE OF WEST WALL FUEL TRUCK 1 PROGRESSING NO.RTH - LOADED EUKES PICKUP TRUCKS 2 750 DUG PARALLEL TO SOUTH SIDE OF NORTH WALL LIGHT TOWERS 13 PASSED DEBRIS TO GATEWAYS 550 THEN TO 365 .. SITE MULE 3 DROPPED PORTION OF WEST WALL DUMP TRUCKS TULLY DRESSED ROAD WITH MILLINGS f" 10 WHEEL DUMP TRUCK DUG OUT MILLINGS WEST OF 750 TON CRANE TO LEVEL FLASHING ARROW BOARD 1 AND SET MATS. I OFFICE TRAILER/GENER. 1 NOTE: TULLY’S PC750 FELL INTO SOUTH PORTION OF CARGO BOXES 3 WEST SLURRY WALL - 1200 PULLED IT UP. FLAT TRUCK PUMP 2 ROLLER RAINMAKER7GENIE LIFT 1 sss Description of Work;
LOADS OUT:91. EUKE LOADS 17________________ LOAD OUT STEEL AND DEBRIS_________ _______ MANNED TARPING AND TRIMMING STATIONS MANNED WATER STATIONS FOR DUST CONTROL MAINTAIN TRAFFIC FLOW IN AND OUT OF AREA EXCAVATE & GRADE CRANE PAD - SET MATS
GRACE CONTRACTING CORP |Approved By:. Title: BY: iFor; SURE!(RlNTENDENT ’
DAILY WORK FORCE REPORT 1203N.xls
Q2,20QQ92
CITY_21MC100_002352229
NYC-WTC_000361552
OCR can misread numbers and units. Confirm readings against the page image before using them.
Ranked by indexed similarity. Reasons describe shared subjects and filing context; check the source records.
NYC-WTC_000429741
Staffing and machinery listings for World Trade Center construction, Dec 2001.
2 shared non-person entities · 1 shared topics · similarity 0.989
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000278623
Night final daily workforce report with labor classifications and equipment.
2 shared non-person entities · 1 shared topics · similarity 0.985
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000280755
Night shift workforce and equipment at World Trade Center, Dec 3, 2001.
2 shared non-person entities · 1 shared topics · similarity 0.982
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000429729
Night final daily workforce and equipment at World Trade Center, Dec 10, 2001.
2 shared non-person entities · 1 shared topics · similarity 0.981
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000305228
Night final daily workforce and equipment at World Trade site, Dec 3, 2001.
2 shared non-person entities · 1 shared topics · similarity 0.981
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000429731
Night shift daily labor/equipment listing for World Trade Center, Dec 9, 2001.
1 shared non-person entities · 1 shared topics · similarity 0.980
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000278690
Night shift daily workforce and equipment at World Trade Center, December 3, 2001.
2 shared non-person entities · 1 shared topics · similarity 0.980
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000291383
December 3, 2001 night final daily work force report for World Trade Center site.
2 shared non-person entities · 1 shared topics · similarity 0.980
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000388366
Night shift daily workforce and equipment at World Trade site, Dec 3, 2001.
2 shared non-person entities · 1 shared topics · similarity 0.980
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000305515
Day FINAL daily workforce and equipment for World Trade Center site, February 2002.
1 shared non-person entities · 1 shared topics · similarity 0.980
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000432438
Night final daily workforce report for World Trade Center site, Nov 3, 2001.
2 shared non-person entities · 1 shared topics · similarity 0.980
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000389436
Final nightly daily workforce and equipment list for World Trade site, Nov 3, 2001.
2 shared non-person entities · 1 shared topics · similarity 0.980
machine-extracted · confidence unavailable · Check page ↗No available related records indexed in this group.
Similar subjects in other documents. Similarity does not establish the same event, measurement or conclusion.
NYC-WTC_000429741
Staffing and machinery listings for World Trade Center construction, Dec 2001.
Similarity score 0.994 (not a probability)
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000278623
Night final daily workforce report with labor classifications and equipment.
Similarity score 0.993 (not a probability)
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000280755
Night shift workforce and equipment at World Trade Center, Dec 3, 2001.
Similarity score 0.991 (not a probability)
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000429729
Night final daily workforce and equipment at World Trade Center, Dec 10, 2001.
Similarity score 0.991 (not a probability)
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000305228
Night final daily workforce and equipment at World Trade site, Dec 3, 2001.
Similarity score 0.990 (not a probability)
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000429731
Night shift daily labor/equipment listing for World Trade Center, Dec 9, 2001.
Similarity score 0.990 (not a probability)
machine-extracted · confidence unavailable · Check page ↗Readers open these alongside this record — through an Ask answer, the same folder, or indexed similarity. Not a claim they are about the same event.
NYC-WTC_000429741
Staffing and machinery listings for World Trade Center construction, Dec 2001.
Similar indexed content
NYC-WTC_000278623
Night final daily workforce report with labor classifications and equipment.
Similar indexed content
NYC-WTC_000280755
Night shift workforce and equipment at World Trade Center, Dec 3, 2001.
Similar indexed content
NYC-WTC_000429729
Night final daily workforce and equipment at World Trade Center, Dec 10, 2001.
Similar indexed content
NYC-WTC_000305228
Night final daily workforce and equipment at World Trade site, Dec 3, 2001.
Similar indexed content