GRACE CONTRACTING CORP. ISMS 6th Road, Whitestone, N.Y. 11357-(718) 767-9000 DATE: 1/30/02 DAY FINAL
DAILY WORK FORCE REPORT
Job Name & Location; World Trade Center Contract No. Weather Conditions
Labor Equipment CLASSIFICATION QUANT. Description MANNED STANDBY IDLE SUPERINTENDENT 1 CAT 966 LOADER 1 PROJECT ENGINEER______________________ 2 CAT 365 GRAPPLER 1 OFFICE ENGINEER CAT 3Z5 GRAPPLER 2 FOREMEN 1 HITACHI 750 GRAPPLER 1 SAFETY OFFICER_________________________ 1 HITACHI 1200 GRAPPLER 1 LABORERS 10 185 CFM COMPRESSOR 1 IRON WORKERS 235 HAMMER HOE RAM 1 LOCAL 14 5 MECHANICS TRUCK 2 LOCAL 15 7 TOOL TRUCK CARPENTER TOOL VAN 1 CARPENTER FOREMAN 1 ROLL OFF TEAMSTERS (FUEL, TRAILER DELIVERY) 1 DUMP TRAILERS TEAMSTERS (FLATBEDS, DUMPS, AND EUKES) 14 LOW BED TRAILER MECHANICS 2 HIGH DECK TRAILERS HOUSE WRECKERS 1 WELDING TRUCK 1 FUEL TRUCK 1 PICKUP TRUCKS 8 LIGHT TOWERS 5 DELIVERIES: AWISCO SITE MULE 3 DUMP TRUCKS 10 WHEEL DUMP TRUCK FLASHING ARROW BOARD OFFICE TRAILER/GENER. 1 CARGO BOXES 4 FLAT TRUCK 1 PUMP 2
LIGHT TOWERS USED FOR 2.5 HOURS
Description of Work:
CONTINUE REMOVING DEBRIS FROM LOWER LEVELS OF WTO, COMPLEX MAINTAIN TRAFFIC FLOW INTO AND OUT OF AREA___________________ RECORD TIMES AND NUMBERS OF TRUCK LOADS OF DEBRIS FROM SITE LOADS OUT: 95 YUKES: 141 DOT LOADS: 95
GRACE CONTRACTING CORP Approved By: BY: Title: For: SUPERINTENDENT
DAILY WORK FORCE REPORT0130D.xls
CITY_21MC100_010385233
NYC-WTC_000356576
OCR can misread numbers and units. Confirm readings against the page image before using them.
Ranked by indexed similarity. Reasons describe shared subjects and filing context; check the source records.
NYC-WTC_000305184
Daily workforce and equipment details for World Trade, Jan 29, 2002.
1 shared non-person entities · 1 shared topics · similarity 0.994
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000342323
Day shift daily workforce and equipment at World Trade site, January 2002.
1 shared non-person entities · 1 shared topics · similarity 0.992
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000429459
Day shift workforce and equipment at the World Trade Center project.
1 shared non-person entities · 1 shared topics · similarity 0.991
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000305509
Day FINAL daily workforce and equipment for World Trade Center site, February 2002.
1 shared non-person entities · 1 shared topics · similarity 0.990
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000356564
Daily labor/equipment roster for World Trade site, Jan 24, 2002.
1 shared non-person entities · 1 shared topics · similarity 0.990
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000419072
Night preliminary daily workforce report for construction at World Trade Center site.
1 shared non-person entities · 1 shared topics · similarity 0.990
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000356570
Daily labor/equipment roster for World Trade site, Jan 27, 2002.
1 shared non-person entities · 1 shared topics · similarity 0.990
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000429460
Night shift daily workforce and equipment at World Trade Center site.
1 shared non-person entities · 1 shared topics · similarity 0.989
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000429415
Day shift staffing and equipment details for World Trade Center project on 1/29/02.
1 shared non-person entities · 1 shared topics · similarity 0.988
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000429417
Day shift labor and equipment counts for World Trade Center site on 1/30/02.
1 shared non-person entities · 1 shared topics · similarity 0.988
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000429395
Day shift daily workforce and equipment details for World Trade site on 1/19/02.
1 shared non-person entities · 1 shared topics · similarity 0.988
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000429397
Day shift daily workforce and equipment details for World Trade site on 1/20/02.
1 shared non-person entities · 1 shared topics · similarity 0.987
machine-extracted · confidence unavailable · Check page ↗No available related records indexed in this group.
Similar subjects in other documents. Similarity does not establish the same event, measurement or conclusion.
NYC-WTC_000305184
Daily workforce and equipment details for World Trade, Jan 29, 2002.
Similarity score 0.997 (not a probability)
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000342323
Day shift daily workforce and equipment at World Trade site, January 2002.
Similarity score 0.996 (not a probability)
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000429459
Day shift workforce and equipment at the World Trade Center project.
Similarity score 0.995 (not a probability)
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000305509
Day FINAL daily workforce and equipment for World Trade Center site, February 2002.
Similarity score 0.995 (not a probability)
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000356564
Daily labor/equipment roster for World Trade site, Jan 24, 2002.
Similarity score 0.995 (not a probability)
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000419072
Night preliminary daily workforce report for construction at World Trade Center site.
Similarity score 0.995 (not a probability)
machine-extracted · confidence unavailable · Check page ↗Readers open these alongside this record — through an Ask answer, the same folder, or indexed similarity. Not a claim they are about the same event.
NYC-WTC_000305184
Daily workforce and equipment details for World Trade, Jan 29, 2002.
Similar indexed content
NYC-WTC_000342323
Day shift daily workforce and equipment at World Trade site, January 2002.
Similar indexed content
NYC-WTC_000429459
Day shift workforce and equipment at the World Trade Center project.
Similar indexed content
NYC-WTC_000305509
Day FINAL daily workforce and equipment for World Trade Center site, February 2002.
Similar indexed content
NYC-WTC_000356564
Daily labor/equipment roster for World Trade site, Jan 24, 2002.
Similar indexed content