Night shift daily crew and equipment list for Grace Contracting at World Trade Center site, January 2002.
1 shared non-person entities · 1 shared topics · similarity 0.995
machine-extracted · confidence unavailable · Check page ↗Night shift daily workforce and equipment at World Trade site, January 2002.
NYC-WTC_000342322OCR status: ok · source: pdftotext
NYC 9/11 Public Portal Document
GRACE CONTRACTING CORP. 151-46 601 Road, Whitestone, N.Y. 11357-(718) 767-9000 DATE: 1/29/02 NIGHT FINAL
DAILY WORK FORCE REPORT
Job Name & Location: World Trade Center Contract No. Weather Conditions
Labor Il Equipment CLASSIFICATION QUANT. Il Description MANNED STANDBY IDLE SUPERINTENDENT 2 CAT 966 LOADER 1 PROJECT ENGINEER 1 CAT 365 GRAPPLER 1 OFFICE ENGINEER CAT 375 GRAPPLER 2 FOREMEN_______________________________ 2 HITACHI 750 GRAPPLER 1 SAFETY OFFICER HITACHI 1200 GRAPPLER 1 LABORERS______________________________ 12 185 CFM COMPRESSOR 1 IRON WORKERS__________________________ 235 HAMMER HOE RAM 1 LOCAL 14 5 MECHANICS TRUCK 1 1 LOCAL 15 6 TOOLTRUCK CARPENTER TOOL VAN CARPENTER FOREMAN____________________ ROLLOFF TEAMSTERS (FUEL, TRAILER DELIVERY) 1 DUMP TRAILERS 8 TEAMSTERS (FLATBEDS. DUMPS. AND EUKES) 14 LOW BED TRAILER 4 MECHANICS 1 EUKES 3 HOUSE WRECKERS WELDING TRUCK FUELTRUCK 1 PICKUP TRUCKS 3 LIGHT TOWERS 5 DELIVERIES: SITE MULE 3 DUMP TRUCKS 10 WHEEL DUMP TRUCK FLASHING ARROW BOARD OFFICE TRAILER/GENER. 1 CARGO BOXES 3 FLAT TRUCK PUMP 2
Description of Work: COMPLETED WORK______________________________________________ CONTINUE REMOVING DEBRIS FROM LOWER LEVELS OF WTC COMPLEX MAINTAIN TRAFFIC FLOW INTO AND OUT OF AREA___________________ RECORD TIMES AND NUMBERS OF TRUCK LOADS OF DEBRIS FROM SITE DELAYS DUE TO NORMAL INSPECTION OF MATERIAL BY FDNY_________ LOADS OUT: 100________________________________________________ YUKESOUT: 118________________________________________________ DOT OUT: 31
GRACE CONTRACTING CORP Approved By: BY: Title: For: SUPERINTENDENT
DAILY WORK FORCE REPORT0129N.xls 02.214777
CITY_21MC100_004028133
NYC-WTC_000342322
OCR can misread numbers and units. Confirm readings against the page image before using them.
Ranked by indexed similarity. Reasons describe shared subjects and filing context; check the source records.
NYC-WTC_000356575
Night shift daily crew and equipment list for Grace Contracting at World Trade Center site, January 2002.
1 shared non-person entities · 1 shared topics · similarity 0.995
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000356577
Night shift daily labor/equipment roster for Grace Contracting at World Trade Center site, January 2002.
1 shared non-person entities · 1 shared topics · similarity 0.993
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000263646
Daily labor/equipment report for World Trade Center construction (1/29/02).
1 shared non-person entities · 1 shared topics · similarity 0.992
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000291340
Night final daily workforce and equipment for World Trade Center, Feb 3, 2002.
1 shared non-person entities · 1 shared topics · similarity 0.992
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000305486
Daily workforce and equipment listing for World Trade Center site, with classifications and quantities.
1 shared non-person entities · 1 shared topics · similarity 0.992
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000429416
Night shift staffing and equipment listings for World Trade Center project on 1/29/02.
1 shared non-person entities · 1 shared topics · similarity 0.991
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000305485
Day final daily workforce and equipment at World Trade Center site, jan 30 2002.
1 shared non-person entities · 1 shared topics · similarity 0.991
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000356572
Daily labor/equipment roster for World Trade site, Jan 28, 2002.
1 shared non-person entities · 1 shared topics · similarity 0.991
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000305484
Night preliminary daily workforce and equipment for World Trade Center site, jan 30 2002.
1 shared non-person entities · 1 shared topics · similarity 0.990
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000305454
Final daily crew and equipment listing for World Trade Center site, Feb 4, 2002.
1 shared non-person entities · 1 shared topics · similarity 0.990
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000356574
Daily labor and equipment tally for Grace Contracting at World Trade Center site, January 2002.
1 shared non-person entities · 1 shared topics · similarity 0.990
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000429456
Night shift daily workforce and equipment listing for World Trade Center construction.
1 shared non-person entities · 1 shared topics · similarity 0.990
machine-extracted · confidence unavailable · Check page ↗No available related records indexed in this group.
Similar subjects in other documents. Similarity does not establish the same event, measurement or conclusion.
NYC-WTC_000356575
Night shift daily crew and equipment list for Grace Contracting at World Trade Center site, January 2002.
Similarity score 0.998 (not a probability)
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000356577
Night shift daily labor/equipment roster for Grace Contracting at World Trade Center site, January 2002.
Similarity score 0.997 (not a probability)
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000263646
Daily labor/equipment report for World Trade Center construction (1/29/02).
Similarity score 0.996 (not a probability)
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000291340
Night final daily workforce and equipment for World Trade Center, Feb 3, 2002.
Similarity score 0.996 (not a probability)
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000305486
Daily workforce and equipment listing for World Trade Center site, with classifications and quantities.
Similarity score 0.996 (not a probability)
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000429416
Night shift staffing and equipment listings for World Trade Center project on 1/29/02.
Similarity score 0.996 (not a probability)
machine-extracted · confidence unavailable · Check page ↗Readers open these alongside this record — through an Ask answer, the same folder, or indexed similarity. Not a claim they are about the same event.
NYC-WTC_000356575
Night shift daily crew and equipment list for Grace Contracting at World Trade Center site, January 2002.
Similar indexed content
NYC-WTC_000356577
Night shift daily labor/equipment roster for Grace Contracting at World Trade Center site, January 2002.
Similar indexed content
NYC-WTC_000263646
Daily labor/equipment report for World Trade Center construction (1/29/02).
Similar indexed content
NYC-WTC_000291340
Night final daily workforce and equipment for World Trade Center, Feb 3, 2002.