NYC-WTC_000322590
Day final workforce and equipment listing for World Trade project, Feb 7, 2002.
1 shared non-person entities · 1 shared topics · similarity 0.995
machine-extracted · confidence unavailable · Check page ↗Final day workforce and equipment listing for World Trade project, Feb 7, 2002.
NYC-WTC_000322587OCR status: ok · source: pdftotext
NYC 9/11 Public Portal Document
GRACE CONTRACTING CORP. 151-45 6th Road. Whitestone. N.Y. 11357-(718) 767-9000 DATE: 2/7/02 DAY FINAL
DAILY WORK FORCE REPORT
Job Name & Location: World Trade Center Contract No. Weather Conditions
Labor Equipment CLASSIFICATION QUANT. Description MANNED STANDBY IDLE SUPERINTENDENT 2 CAT 966 LOADER 1 PROJECT ENGINEER 2 CAT 365 GRAPPLER 1 FOREMEN 1 CAT 375 BUCKET 1 SAFETY OFFICER CAT 375 GRAPPLER 1 LABORERS__________________________ 14 HITACHI 750 GRAPPLER 1 IRON WORKERS HITACHI 1200 GRAPPLER 1 LOCAL 14 4 185 CFM COMPRESSOR •SEE NOTE LOCAL 15 ■5 235 HAMMER HOE RAM 1 CARPENTER MECHANICS TRUCK 2 CARPENTER FOREMAN 2 TOOL TRUCK 1 TEAMSTERS (FUEL)____________________ TOOL VAN______________ 1 TEAMSTERS (FLATBEDS, DUMPS, AND EUKES) ROLLOFF MECHANICS 2 DUMP TRAILERS 8 HOUSE WRECKERS LOW BED TRAILER HIGH DECK TRAILERS 2 WELDING TRUCK________ 1 FUEL TRUCK 1 DELIVERIES: AWISCO PICKUP TRUCKS 8 LIGHT TOWERS 5 NOTE: LIGHT TOWERS USED 2.S HOURS SITE MULE 3 185 CFM COMPRESSOR RAN UNMANNED DUMP TRUCKS 10 WHEEL DUMP TRUCK FLASHING ARROW BOARD 1 OFFICE TRAILER7GENER. 1 ^OTE: TRUCK 62 IS BEING USED BY TULLY FROM 2:30 TIL CARGO BOXES 4 END OF SHIFT. I FLAT TRUCK 1 TRUCK 99 IS USED BY TULLY ALL DAY UNDER PUMP 2 THE PEDESTRIAN BRIDGE
FLASHING ARROW BOARD PLACED AT PIER 25 AT 1:30 PM
Description of Work:__________________________________________________ 'COMPLETED WORK CONTINUED REMOVING DEBRIS FROM LOWER LEVELS OF WTC COMPLEX MAINTAINED TRAFFIC FLOW INTO AND OUT OF AREA___________________ CONTINUED LOGGING TRUCKS AND NUMBER OF LOADS OUT OF SITE LOADS OUT: 77_____________________________________________________ EUKESOUT: 121
GRACE CONTRACTING COiy| Approved By: Title: For: BY:
SUPERINTENDENT I DAILY WORK FORCE REPORT0207D.xls
CITY_21MC100_004541608
NYC-WTC_000322587
OCR can misread numbers and units. Confirm readings against the page image before using them.
Ranked by indexed similarity. Reasons describe shared subjects and filing context; check the source records.
NYC-WTC_000322590
Day final workforce and equipment listing for World Trade project, Feb 7, 2002.
1 shared non-person entities · 1 shared topics · similarity 0.995
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000268645
Daily labor and equipment assignments for World Trade Center project site, Feb 7, 2002.
1 shared non-person entities · 1 shared topics · similarity 0.994
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000429463
Day shift workforce and equipment at World Trade Center construction.
2 shared non-person entities · 1 shared topics · similarity 0.994
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000419180
Day final workforce and equipment for 2/7/02 at World Trade site.
2 shared non-person entities · 1 shared topics · similarity 0.994
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000305128
Daily labor/equipment summary for World Trade Center site.
2 shared non-person entities · 1 shared topics · similarity 0.993
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000305187
Day final workforce and equipment at World Trade, Jan 31, 2002.
1 shared non-person entities · 1 shared topics · similarity 0.992
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000252295
Day shift daily workforce and equipment roster for World Trade Center site.
2 shared non-person entities · 1 shared topics · similarity 0.992
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000305122
Daily labor/equipment summary for World Trade Center site.
1 shared non-person entities · 1 shared topics · similarity 0.992
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000290784
Daily workforce roster for Grace Contracting at World Trade site with crew and equipment details.
2 shared non-person entities · 1 shared topics · similarity 0.991
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000305454
Final daily crew and equipment listing for World Trade Center site, Feb 4, 2002.
1 shared non-person entities · 1 shared topics · similarity 0.991
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000419068
Night final daily workforce report showing supervisory and crew counts with equipment.
1 shared non-person entities · 1 shared topics · similarity 0.991
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000305503
Night final daily workforce and equipment listing for World Trade Center site.
2 shared non-person entities · 1 shared topics · similarity 0.991
machine-extracted · confidence unavailable · Check page ↗No available related records indexed in this group.
Similar subjects in other documents. Similarity does not establish the same event, measurement or conclusion.
NYC-WTC_000322590
Day final workforce and equipment listing for World Trade project, Feb 7, 2002.
Similarity score 0.998 (not a probability)
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000268645
Daily labor and equipment assignments for World Trade Center project site, Feb 7, 2002.
Similarity score 0.997 (not a probability)
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000429463
Day shift workforce and equipment at World Trade Center construction.
Similarity score 0.997 (not a probability)
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000419180
Day final workforce and equipment for 2/7/02 at World Trade site.
Similarity score 0.997 (not a probability)
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000305128
Daily labor/equipment summary for World Trade Center site.
Similarity score 0.996 (not a probability)
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000305187
Day final workforce and equipment at World Trade, Jan 31, 2002.
Similarity score 0.996 (not a probability)
machine-extracted · confidence unavailable · Check page ↗Readers open these alongside this record — through an Ask answer, the same folder, or indexed similarity. Not a claim they are about the same event.
NYC-WTC_000322590
Day final workforce and equipment listing for World Trade project, Feb 7, 2002.
Similar indexed content
NYC-WTC_000268645
Daily labor and equipment assignments for World Trade Center project site, Feb 7, 2002.
Similar indexed content
NYC-WTC_000429463
Day shift workforce and equipment at World Trade Center construction.
Similar indexed content
NYC-WTC_000419180
Day final workforce and equipment for 2/7/02 at World Trade site.
Similar indexed content
NYC-WTC_000305128
Daily labor/equipment summary for World Trade Center site.
Similar indexed content