Draft: environmental monitoring plan for WTC debris

Machine-extracted title · confidence 50%

Draft plan for environmental monitoring of exposure to fibers after WTC collapse.

NYC-WTC_000302886–000302921
Page image
Page image not rendered yet.
The pipeline renders page images incrementally; check back or read the OCR text alongside.
OCR text

OCR status: ok · source: pdftotext

NYC 9/11 Public Portal Document

C. ASSESSMENT AND OVERSIGHT

Cl. ASSESSMENTS AND RESPONSE ACTIONS

Quality Assurance assessments performed during this project will include the following:

1) Oversight of field sampling activities 2) Oversight of sample handling and chain of custody procedures 3) Laboratory inspections

The following individuals or their delegates are authorized to perform any of the assessments above:

Project Manager Technical Lead NYC QA Coordinator

Assessment of field sampling and other project activities may occur at any time and without prior notification. The frequency of such assessments will be no less than once per week during active field work, and may be more often, especially if issues or problems are detected during an assessment. Each of the individuals above has authority to specify any appropriate response action that may be deemed necessary to resolve problems detected during the assessments. This could range from a simple review of approved SOPs with field staff to address minor problems, up to a temporary stop work order to provide time for senior project managers to address more significant issues.

C2. REPORTS TO MANAGEMENT

The Project Director will provide regular verbal reports on project status. These reports will cover data quality assessment issues, and will identify any significant problems and recommended solutions. The Project Director will prepare a complete written QA report at the end of the project, and may prepare interim written reports at any time during the project, as needed to document important issues and actions.

D. DATA VALIDATION AND USABILITY

DI. DATA REVIEW, VERIFICATION, and VALIDATION

Data Verification

Data verification is a consistent and systematic process that determines whether the data have been collected in accordance to the specifications as listed in the approved Quality Assurance Project Plan (QAPP). This process is independent of data validation, and is conducted at various

CITY_21MC1OO_OO9O29O53

NYC-WTC_000302914

OCR can misread numbers and units. Confirm readings against the page image before using them.

NYC-WTC_000302914Source: NYC Law Department, mirrored locally

Related records

Browse subjects →

Ranked by indexed similarity. Reasons describe shared subjects and filing context; check the source records.

Same-box records

Filed elsewhere

More like this page

Similar subjects in other documents. Similarity does not establish the same event, measurement or conclusion.

Others also read

Readers open these alongside this record — through an Ask answer, the same folder, or indexed similarity. Not a claim they are about the same event.

Compare copies and versions →