GRACE CONTRACTING CORP. 151.45 eih Road. Whiiestone. nY 11357-(718) 737-9000 DATE: DECEMBER 13, 2001 (DAY FINAL)
DAILY WORK FORCE REPORT
lob Name & Location: World Trade Cenler Contract No. Weather Conditions I I Labor______ Equipment ; CLASSIFICATION QUANT. Description MANNED STANDBY IDLE SUPERINTENDENT 1 CAT 986 LOADER 1 PROJECT ENGINEER ; 1 CAT 446 BACKHOE 1 OFFICE ENGINEER CAT 973 LOADER 1 FOREMEN 1 CAT 365 GRAPPLER 1 SAFETY OFFICER ' CAT 375 GRAPPLER 1 LABORERS 26 HITACHI 750 GRAPPLER 1 IRON WORKERS 1 HITACHI 550 GRAPPLER 1 LOCAL 14 5 HITACHI 550 GRAPPLER 1 LOCAL 15 10 HITACHI 1200 GRAPPLER 1 CARPENTER 1 185 CFM COMPRESSOR 1 CARPENTER FOREMAN 2 235 HAMMER HOE RAM 1 TEAMSTERS 1 MECHANICS TRUCK 2 MECHANICS 2 TOOL TRUCK HOUSE WRECKERS 8 TOOL VAN 1 ROLL OFF DUMP TRAILERS LOW BED TRAILER DELIVERIES: TRIBORO HARDWARE HIGH DECK TRAILERS AUSTER RUBBER WELDING TRUCK 1 FUEL TRUCK 1 PICKUP TRUCKS 8 LIGHT TOWERS_________ 13 SITE MULE 3 DUMP TRUCKS 10 WHEEL DUMP TRUCK FLASHING ARROW BOARD 1 OFFICE TRAILER/GENER. 1 CARGO BOXES 3 FLAT TRUCK 1 PUMP 2 LIGHT TOURS USED FOR 3 HOURS ROLLER 1 RAINMAKEFOGENIE LIFT 1
Description of Work: LOADS OUT: 40 YUKES OUT: £5 DELAYS GATEWAY 600 GRACE 550 DUE! TO SEARCH AND RECOVERY MANNED TARPING AND TRIMMING STATIONS_____________________ MANNED WATER STATIONS FOR DUST CONTROL__________________ MAINTAIN TRAFFIC FLOW IN AND OUT OF AREA___________________ CONTINUE REMOVING DEBRIS FROM LOWER LEVELS OF TOWER 2 INSTALLATION OF GPS SYSTEMS________________________________ PUT UP CRANE MATS________________ ELEVATIONS: ALL MACHINES LEVEL S-5 253
GRACE CONTRACTING CORP^----- x Approved By: Title: For: superintendent'
DAILY WORK FORCE REPORT 1213D.xls
I
CITY_21MC100_003180487
NYC-WTC_000291366
OCR can misread numbers and units. Confirm readings against the page image before using them.
Ranked by indexed similarity. Reasons describe shared subjects and filing context; check the source records.
NYC-WTC_000386652
Day shift daily workforce and equipment listing for World Trade site, Dec 13, 2001.
2 shared non-person entities · 1 shared topics · similarity 0.977
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000280776
Daily workforce and equipment at World Trade Center, Dec 15, 2001.
2 shared non-person entities · 1 shared topics · similarity 0.975
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000388260
Day shift daily workforce for World Trade Center site, November 26, 2001.
2 shared non-person entities · 1 shared topics · similarity 0.974
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000278986
Day shift daily workforce report for World Trade Center site, December 12, 2001.
2 shared non-person entities · 1 shared topics · similarity 0.974
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000305389
Day shift labor and equipment counts for World Trade Center site.
2 shared non-person entities · 1 shared topics · similarity 0.974
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000389489
Day shift daily workforce and equipment at World Trade site, Dec 13, 2001.
2 shared non-person entities · 1 shared topics · similarity 0.973
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000388382
Day shift daily workforce at World Trade Center, Dec 13, 2001.
2 shared non-person entities · 1 shared topics · similarity 0.973
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000269237
Day or night shift daily workforce and equipment at World Trade site, Jan 2, 2002.
2 shared non-person entities · 1 shared topics · similarity 0.973
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000237663
Grace Contracting Corp. daily log of laborers and equipment at the World Trade site for January 20, 2002 day shift.
1 shared non-person entities · 1 shared topics · similarity 0.973
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000280784
Day shift daily workforce and equipment at World Trade Center, Dec 19, 2001.
2 shared non-person entities · 1 shared topics · similarity 0.973
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000291372
Day shift daily work force report for World Trade Center site, Dec 10, 2001.
2 shared non-person entities · 1 shared topics · similarity 0.973
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000432508
Daily workforce and equipment listing for World Trade Center site, Dec 13, 2001.
2 shared non-person entities · 1 shared topics · similarity 0.973
machine-extracted · confidence unavailable · Check page ↗No available related records indexed in this group.
Similar subjects in other documents. Similarity does not establish the same event, measurement or conclusion.
Page similarity is temporarily unavailable or this page has no indexed vector.
Readers open these alongside this record — through an Ask answer, the same folder, or indexed similarity. Not a claim they are about the same event.
NYC-WTC_000386652
Day shift daily workforce and equipment listing for World Trade site, Dec 13, 2001.
Similar indexed content
NYC-WTC_000280776
Daily workforce and equipment at World Trade Center, Dec 15, 2001.
Similar indexed content
NYC-WTC_000388260
Day shift daily workforce for World Trade Center site, November 26, 2001.
Similar indexed content
NYC-WTC_000278986
Day shift daily workforce report for World Trade Center site, December 12, 2001.
Similar indexed content
NYC-WTC_000305389
Day shift labor and equipment counts for World Trade Center site.
Similar indexed content