GRACE CONTRACTING CORP. 151.45 6th Road, Whitestone, N.Y. 11357-(718) 767-9000 DATE: 2/13/02 DAY FINAL
DAILY WORK FORCE REPORT
Job Name & Location: World Trade Center Contract No. Weather Conditions
Labor Equipment llsUPERINTENDENT CLASSIFICATION QUANT. Description .MANNED STANDBY idle' 2 CAT 966 LOADER 1 FOREMEN 1 CAT 365 GRAPPLER i PROJECT ENGINEER 2 CAT 375 BUCKET 1 SAFETY OFFICER 1 CAT 375 GRAPPLER 1 LABORERS 16 HITACHI 750 GRAPPLER 7 IRON WORKERS HITACHI 1200 GRAPPLER 1 LOCAL 14 4 185 CFM COMPRESSOR ‘SEE NOTE LOCAL 15 6 235 HAMMER HOE RAM 1 CARPENTER MECHANICS TRUCK 2 CARPENTER FOREMAN 1 TOOLTRUCK TEAMSTERS (FUEL) 1 TOOL VAN MECHANICS 2 ROLL OFF HOUSE WRECKERS DUMP TRAILERS LOW BED TRAILER HIGH DECK TRAILERS DELIVERIES: TRIBORO HARDWARE WELDING TRUCK 1 FUEL TRUCK 1 =zz==z ‘NOTE: 185 CFM COMPRESSOR RUNNING UNMANNED PICKUP TRUCKS LIGHT TOWERS 6 5 SITE MULE 2 15 TEAMSTERS (11 DUMP TRAILERS, 4 EUKES ) DUMP TRUCKS 10 WHEEL DUMP TRUCK FLASHING ARROW BOARD 1 "NOTE: TRUCK 63 DID NOT START RUNNING DEBRIS UNTIL OFFICE TRAILER/GENER. 1 10:15 AM I CARGO BOXES 4 TRUCK #7 STOPPED RUNNING DEBRIS @ 10:30 AM FLAT TRUCK AND BEGAN RUNNING STONE FOR EROC FROM PUMP 2 QUEENS I TRUCK 72 PARKED @ 2:15 PM, WILLNOT BE RUNNINC ANYMORE LOADS. FAMILY EMERGENCY H " —i—^—1.1 1.. I ——I— a—BSSSBSS=
Description of Work: COMPLETED WORK CONTINUE REMOVING DEBRIS FROM LOWER LEVELS OF WTC COMPLEX MAINTAIN TRAFFIC FLOW INTO AND OUT OF AREA____________________ CONTINUE LOGGING TRUCKS AND NUMBER OF LOADS OUT OF SITE LOADS OUT; 102
GRACE CONTRACTING CORP Approved By: BY: Title: For: SUPERINTENDENT
DAILY WORK FORCE REPORT0213D.xls
CITY_21MC10 0_0 0 49'72775
NYC-WTC_000291354
OCR can misread numbers and units. Confirm readings against the page image before using them.
Ranked by indexed similarity. Reasons describe shared subjects and filing context; check the source records.
NYC-WTC_000429470
Day shift workforce and equipment for World Trade Center construction.
1 shared non-person entities · 1 shared topics · similarity 0.998
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000305135
Day shift daily workforce and equipment at World Trade site, Feb 13, 2002.
1 shared non-person entities · 1 shared topics · similarity 0.997
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000429469
Day shift workforce and equipment at World Trade Center project.
1 shared non-person entities · 1 shared topics · similarity 0.994
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000268621
Daily workforce and equipment roster for World Trade Center site, listing crew and machinery.
2 shared non-person entities · 1 shared topics · similarity 0.993
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000278693
Daily workforce roster and equipment listings for World Trade construction site, Feb 2002.
2 shared non-person entities · 1 shared topics · similarity 0.993
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000291336
Day final daily workforce and equipment for World Trade Center, Feb 13, 2002.
1 shared non-person entities · 1 shared topics · similarity 0.993
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000237703
Day shift final daily work force and equipment log for Grace Contracting Corp. at the World Trade Center site.
1 shared non-person entities · 1 shared topics · similarity 0.992
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000291351
Day shift workforce and equipment at World Trade Center, Feb 11, 2002.
1 shared non-person entities · 1 shared topics · similarity 0.992
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000290058
Day shift workforce and equipment roster for World Trade Center site.
1 shared non-person entities · 1 shared topics · similarity 0.992
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000268625
Daily labor and equipment counts for World Trade Center site work.
1 shared non-person entities · 1 shared topics · similarity 0.992
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000322149
Day final daily workforce and equipment at World Trade Center site, February 14, 2002.
1 shared non-person entities · 1 shared topics · similarity 0.992
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000266657
Daily workforce roster for World Trade Center site shift, Grace Contracting.
1 shared non-person entities · 1 shared topics · similarity 0.992
machine-extracted · confidence unavailable · Check page ↗No available related records indexed in this group.
Similar subjects in other documents. Similarity does not establish the same event, measurement or conclusion.
Page similarity is temporarily unavailable or this page has no indexed vector.
Readers open these alongside this record — through an Ask answer, the same folder, or indexed similarity. Not a claim they are about the same event.
NYC-WTC_000429470
Day shift workforce and equipment for World Trade Center construction.
Similar indexed content
NYC-WTC_000305135
Day shift daily workforce and equipment at World Trade site, Feb 13, 2002.
Similar indexed content
NYC-WTC_000429469
Day shift workforce and equipment at World Trade Center project.
Similar indexed content
NYC-WTC_000268621
Daily workforce and equipment roster for World Trade Center site, listing crew and machinery.
Similar indexed content
NYC-WTC_000278693
Daily workforce roster and equipment listings for World Trade construction site, Feb 2002.
Similar indexed content