GRACE CONTRACTING CORP. 151-45 Bth Road, Whitestone, N.Y. 11357-(718) 767-9000 DATE: 2/12/02 DAY FINAL
DAILY WORK FORCE REPORT
Job Name & Location: World Trade Center IContract No. leather Conditions
Labor I Equipment CLASSIFICATION QUANT. I Description MANNED STANDBY IDLE [SUPERINTENDENT 2 CAT 966 LOADER 1 FOREMEN 1 CAT 365 GRAPPLER 1 PROJECT ENGINEER 2 |CAT 375 BUCKET 1 SAFETY OFFICER 1 CAT 375 GRAPPLER 1 LABORERS 14 HITACHI 750 GRAPPLER ~ 1 IRON WORKERS HITACHI 1200 GRAPPLER' 1 LOCAL 14 4 185 CFM COMPRESSOR ‘SEE NOTE LOCAL 15 5 |235 HAMMER HOE RAM " 1 ■ CARPENTER MECHANICS TRUCK 2 CARPENTER FOREMAN 1 TOOL TRUCK TEAMSTERS (FUEL) 1 TOOL VAN MECHANICS 2 ROLL OFF HOUSE WRECKERS DUMP TRAILERS LOW BED TRAILER HIGH DECK TRAILERS IDELIVERIES: WELDING TRUCK 1 FUEL TRUCK 1 PICKUP TRUCKS 6 INOTE: 185 CFM COMPRESSOR RUNNING UNMANNED [light towers 5 SITE MULE 2 |14 TEAMSTERS (10 DUMP TRAILERS, 4 EUKES ) DUMP TRUCKS 10 WHEEL DUMP TRUCK 'NOTE: TRUCK 63 WAS BEING FILLED WITH DIRT FROM THE IlFLASHING ARROW BOARD TRENCH WORK AT LIBERTY & WEST. WILL NOT DO AS OFFICE TRAILER/GENER. 1 MANY LOADS AS THE OTHER TRUCKS CARGO BOXES 4 FLAT TRUCK
I DELAYS: TRUCK 99 WAS DOWN FROM 10:00 AM TO 12:00 PM PUMP 2 WITH AIR TANK PROBLEM. & TRUCK 67 WAS DOWN FROM 11.00 TO 12:30 PM WITH NO HEADLIGHTS & A FLAT TIRE
Description of Work;
CONTINUE REMOVING DEBRIS FROM LOWER LEVELS OF WTC COMPLEX MAINTAIN TRAFFIC FLOW INTO AND OUT OF AREA____________________ CONTINUE LOGGING TRUCKS AND NUMBER OF LOADS OUT OF SITE LOADS OUT: 77
GRACE CONTRACTING CORP Approved By; BY: Title: For: SUPERINTENDENT
DAILY WORK FORCE REPORT0212D.xls
CITY_21MC100_004972773
NYC-WTC_000291353
OCR can misread numbers and units. Confirm readings against the page image before using them.
Ranked by indexed similarity. Reasons describe shared subjects and filing context; check the source records.
NYC-WTC_000429469
Day shift workforce and equipment at World Trade Center project.
1 shared non-person entities · 1 shared topics · similarity 0.987
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000305134
Day shift daily workforce and equipment at World Trade site, Feb 12, 2002.
1 shared non-person entities · 1 shared topics · similarity 0.987
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000268616
Daily workforce and equipment roster with labor and equipment details for World Trade Center site.
1 shared non-person entities · 1 shared topics · similarity 0.987
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000237703
Day shift final daily work force and equipment log for Grace Contracting Corp. at the World Trade Center site.
1 shared non-person entities · 1 shared topics · similarity 0.985
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000266676
Day shift labor/equipment roster for World Trade Center, Mar 1, 2002.
1 shared non-person entities · 1 shared topics · similarity 0.985
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000389563
Day final daily workforce and equipment listing for World Trade site, Feb 2002.
1 shared non-person entities · 1 shared topics · similarity 0.984
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000432600
Night shift workforce and equipment at World Trade Center, Feb 2002.
1 shared non-person entities · 1 shared topics · similarity 0.984
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000360485
Daily workforce roster listing personnel and equipment at site.
1 shared non-person entities · 1 shared topics · similarity 0.984
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000291354
Night shift workforce and equipment for World Trade Center, Dec 13-15 2001.
1 shared non-person entities · 1 shared topics · similarity 0.984
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000429470
Day shift workforce and equipment for World Trade Center construction.
1 shared non-person entities · 1 shared topics · similarity 0.983
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000305135
Day shift daily workforce and equipment at World Trade site, Feb 13, 2002.
1 shared non-person entities · 1 shared topics · similarity 0.982
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000278693
Daily workforce roster and equipment listings for World Trade construction site, Feb 2002.
1 shared non-person entities · 1 shared topics · similarity 0.982
machine-extracted · confidence unavailable · Check page ↗No available related records indexed in this group.
Similar subjects in other documents. Similarity does not establish the same event, measurement or conclusion.
Page similarity is temporarily unavailable or this page has no indexed vector.
Readers open these alongside this record — through an Ask answer, the same folder, or indexed similarity. Not a claim they are about the same event.
NYC-WTC_000429469
Day shift workforce and equipment at World Trade Center project.
Similar indexed content
NYC-WTC_000305134
Day shift daily workforce and equipment at World Trade site, Feb 12, 2002.
Similar indexed content
NYC-WTC_000268616
Daily workforce and equipment roster with labor and equipment details for World Trade Center site.
Similar indexed content
NYC-WTC_000237703
Day shift final daily work force and equipment log for Grace Contracting Corp. at the World Trade Center site.
Similar indexed content
NYC-WTC_000266676
Day shift labor/equipment roster for World Trade Center, Mar 1, 2002.
Similar indexed content