DEP SPDES progress report, West-of-Hudson plants, 2001

Machine-extracted title · confidence 49%

Quarterly progress on upgrades for non-City owned SPDES plants in NYC Watershed, Oct 2001.

NYC-WTC_000291015–000291021
Page image
Page image not rendered yet.
The pipeline renders page images incrementally; check back or read the OCR text alongside.
OCR text

OCR status: ok · source: pdftotext

NYC 9/11 Public Portal Document

PROJECT TIMETABLE

The WWTP Owner shall undertake and fully perform the Scope of Work upon the Commencement Date as defined in Section 1.03 (A) of this Agreement, in accordance with the following Schedule of Work:

MILESTONE ACTIVITY DESCRIPTION ACTIVITY DURATION

Ml Select ENGINEER(s)/ 2 months from Commencement Date Distribute RFP

M2 Receive ENGINEER(s) 2 months from WWTP Owner’s Proposals and submit to EEC distribute of RFP (WWTP Owner’s Scope of Work Subtask 1.2 (A))

M3 Submit WWTP OWNER/ 1 month from receipt of NYCDEP’s ENGINEER Contract to EEC approval of selected Engineer’s Proposal (WWTP Owner’s Scope of Work Subtask 1.2 (B))

M4 Submit Approval CUP 4 months from date EEC authorizes WWTP owner to execute Engineer’s Contract (WWTP Owner’s Scope of Work Subtask 1.3 (C))

M5 Submit Approvable Facility Plan 3 months from receipt of NYCDEP approval of CUP and authorization to proceed from EEC (WWTP Owner’s Scope of Work Subtask 2.1 (F))

M6 Submit Approval PUP 4 months from receipt of NYCDEP approval of Facility Plan (WWTP Owner’s Scope of Work Subtask 2.2 (C))

M7 Submit Approval FUP 1 month from receipt of NYCDEP approval of PUP (WWTP Owner’s Cope of Work Subtask 2,2 (K))

M8 Submit WWTP OWNER/ 2 months from receipt of EFC Contractor Agreement(s) Notice to Proceed with Bid Solicitation (WWTP Owner’s Scope of Work Subtask 2.3 (D))

M9 Submit Functional Completion 9 months from Notice to Proceed Certification with Execution of Contract(s) and Construction (WWTP Owner’s Scope of Work Subtask 3.2 (A))

MIO Submit Construction Close-Out 30 business days from NYCDEP’s Documents written authorization to commence Startup and Performance and to proceed with Project Close-Out (WWTP Owner’s Scope of Work Subtask 4.4 (B))

NYC-WTC_000291017

OCR can misread numbers and units. Confirm readings against the page image before using them.

NYC-WTC_000291017Source: NYC Law Department, mirrored locally

Related records

Browse subjects →

Ranked by indexed similarity. Reasons describe shared subjects and filing context; check the source records.

Same-box records

Filed elsewhere

More like this page

Similar subjects in other documents. Similarity does not establish the same event, measurement or conclusion.

Others also read

Readers open these alongside this record — through an Ask answer, the same folder, or indexed similarity. Not a claim they are about the same event.

NYC-WTC_000291022

Progress report on technical support plan for wastewater treatment plants, period Jul–Sep 2001.