NYC Law Department release
Independent mirror · updated as the City releases more · v1.5.1
☕ Buy me a coffee
← Document results/Unboxed/No folder label
Document / 4 pages

Testwell Laboratories project letter, NYC lease

Machine-extracted title · confidence 21%

Testwell Laboratories submission for lease-related testing, City records.

NYC-WTC_000282175–000282178
Page image
Page image not rendered yet.
The pipeline renders page images incrementally; check back or read the OCR text alongside.
OCR text

OCR status: ok · source: pdftotext

NYC 9/11 Public Portal Document

TIL TESTWELT LABORATORIES.INC. Regarding: Mr. Michael Deane Bovis Lend Lease LMB, Inc. Fungal Inspection and Prevention 55 Church Street New York, New York June 6, 2002 Page 2

majority of the curtainwall was damaged or destroyed and to the kitchen area where there are likely sources of moisture. No standing water was observed on floors 3, 4 or 5.

The lower levels (C and SC) were inspected and signs of fungal growth were observed in the housekeeping office area(s) located on the Cellar level, along the west foundation wall. Fungal growth was observed concentrated on the furred out drywall partition in several of the areas. Other surfaces within the housekeeping office proper were also observed to have visible fungal growth, including a leather chair and carpeting.

Standing water has been observed in the past in several lower level areas including the laundry area and electrical equipment room.

Collection of Samples for Presence of Fungal Contamination Samples to determine the presence of viable fungal contamination were collected from the following materials:

Piping system insulation jacket (ASJ) that indicated visible fungal growth located within a mechanical pipe chase on the 50'” floor.

Drywall from mechanical chase indicating fungal growth on 50’” floor.

Material from leather chair located in housekeeping office on cellar level.

Acoustic duct lining from HVAC #3 located in the 6'” floor MER and feeding the 3'" floor.

These samples have been submitted to the laboratory for incubation and analysis. We anticipate having results on the testing on or about June 12'”.

Recommended Actions to Prevent Fungal Growth As fungal growth has been observed in several areas of the building, it is important to reduce or eliminate the host conditions for further growth. To that end, we recommend that HVAC systems be made operational to circulate air and provide conditioning to eliminate moisture in the air. As the building is currently undergoing decontamination of asbestos fibers, this activity should be limited to those areas where such decontamination has already been performed.

Prior to re-starting, the HVAC systems should be re-commissioned in accordance with the procedures established by Cosentini Associates, including cleaning of the HVAC units and related ductwork and installing new filters.

Mechanical chases on the 50'”, 45'” and every five floors downward thereafter. should be opened and all vertical penetrations sealed, with an appropriate material. Un-insulated piping within the mechanical chaseF'should be insulated to prevent condensation. Drain pans in the fan coil units should be checked to

CITY_21MC100_002942387

NYC-WTC_000282177

OCR can misread numbers and units. Confirm readings against the page image before using them.

NYC-WTC_000282177Source: NYC Law Department, mirrored locally

Related records

Browse subjects →

Ranked by indexed similarity. Reasons describe shared subjects and filing context; check the source records.

Same-box records

Filed elsewhere

More like this page

Similar subjects in other documents. Similarity does not establish the same event, measurement or conclusion.

Buildings in this record

Machine-extracted building matches; verify each source. Buildings, never households.

Others also read

Readers open these alongside this record — through an Ask answer, the same folder, or indexed similarity. Not a claim they are about the same event.

Compare copies and versions →