Daily Work Force Report, Grace Contracting, Dec 9 2001

Machine-extracted title · confidence 32%

World Trade Center site staffing and machinery, Grace Contracting, December 9, 2001.

NYC-WTC_000280000
Page image
Page image not rendered yet.
The pipeline renders page images incrementally; check back or read the OCR text alongside.
OCR text

OCR status: ok · source: pdftotext

NYC 9/11 Public Portal Document

GRACE CONTRACTING CORP. 15M5 6th Road, Whitestone. N.Y. 11357-(718) 767-9000 DATE: SUNDAY 12-9-01 DAYMV

DAILY WORK FORCE REPORT "I

Job Name & Location: World Trade Center Contract No. Weather Conditions

SUPERINTENDENT Labor CLASSIFICATION Il QUANT. 11 Equipment Description CAT 966 LOADER MANNED STANDBY 1 1 a PROJECT ENGINEER CAT 446 BACKHOE OFFICE ENGINEER CAT 973 LOADER 1 FOREMEN 1 CAT 365 GRAPPLER 1 SAFETY OFFICER CAT 375 GRAPPLER 1 LABORERS 27 HITACHI 750 GRAPPLER 1 IRON WORKERS HITACHI 550 GRAPPLER 1 LOCAL 14 4 HITACHI 550 GRAPPLER 1 LOCAL 15 9 HITACHI 1200 GRAPPLER 1 CARPENTER 185 CFM COMPRESSOR 1 CARPENTER FOREMAN 2 235 HAMMER HOE RAM 1 TEAMSTERS 11 MECHANICS TRUCK 2 MECHANICS 2 TOOL TRUCK 1 HOUSE WRECKERS TOOL VAN 1 ROLL OFF DUMP TRAILERS 8 LOW BED TRAILER DELIVERIES: ' HIGH DECK TRAILERS 2 ■ WELDING TRUCK 1 ' FUEL TRUCK 1 ■ PICKUP TRUCKS 1 ■ LIGHT TOWERS 13 ■ SITE MULE 3 ' DUMP TRUCKS ■ 10 WHEEL DUMP TRUCK ' FLASHING ARROW BOARD 1 ■ OFFICE TRAILER/GENER. 1 ■ CARGO BOXES 3 ■ FLAT TRUCK ■ PUMP 2 ‘ ROLLER ■ RAINMAKER/GENIE LIFT 1

Description of Work:______________________________________________________________________________________ LOADS OUT: 93________________________________________________________________________________________ LOAD OUT STEEL AND DEBRIS__________________________________________________________________________ MAN TARPING AND TRIMMING STATIONS_________________________________________________________________ MAINTAIN TRAFFIC FLOW IN AND OUT OF AREA___________________________________________________________ CONTINUE REMOVING DEBRIS FROM LOWER LEVELS OF NW CORNER OF TOWER 2 TO MEET AMEC'S ROADWAY CONTINUE BURNING OF THE SW CORNER COLUMN BEAMS________________________________________________ ELEVATIONS: ALL MACHINES LEVEL B-5 253 ________________________________________________________ SEVERAL BRIEF DELAYS FOR FDNY RECOVERY THROUGHOUT THE DAY

GRACE CONTRACTING CORP , Approved By: Title: ~BY: For; SUPERINTEN^NT

DAILY WORK FORCE REPORT1209D.xls

CITY_21MC100_001383006 NYC-WTC_000280000

OCR can misread numbers and units. Confirm readings against the page image before using them.

NYC-WTC_000280000Source: NYC Law Department, mirrored locally

Related records

Browse subjects →

Ranked by indexed similarity. Reasons describe shared subjects and filing context; check the source records.

Same-box records

Filed elsewhere

No available related records indexed in this group.

More like this page

Similar subjects in other documents. Similarity does not establish the same event, measurement or conclusion.

Others also read

Readers open these alongside this record — through an Ask answer, the same folder, or indexed similarity. Not a claim they are about the same event.

NYC-WTC_000280004

World Trade Center workforce and equipment data for December 4, 2001.

Similar indexed content

Compare copies and versions →