GRACE coi •RACTING CORP.
151-45 6th Road, WW itone, N.Y. 113S7-(718) 767-9000 DATE: JA NUARY 4, 2002 NIGHT [FINAL]
DAILY WORK FORCE REPORT
Job Name & Loc ion: World Trade Center
Contract No.
Weather Con dil ns: Clear and cold
Labor Equipment
CLASSIFICATION QUANT. Description MANNED STANDBY IDLE
SUPERINTENDE F 2 CAT 966 LOADER 1
PROJECT ENGII lER CAT 446 BACKHOE 1
OFFICE ENGINE CAT 973 LOADER 1
FOREMEN 2 CAT 365 GRAPPLER 1
SAFETY OFFICE CAT 375 GRAPPLER 1
LABORERS 20 CAT 375 GRAPPLER 1
IRON WORKERS HITACHI 750 GRAPPLER 1
LOCAL 14 5 HITACHI 550 BUCKET 1
LOCAL 15 8 HITACHI 1200 GRAPPLER 1
CARPENTER 185CFM COMPRESSOR 1
CARPENTER FC EMAN 235 HAMMER HOE RAM 1
TEAMSTERS 1 MECHANICS TRUCK 1
MECHANICS 2 TOOL TRUCK
HOUSE WRECKI tS 7 TOOL VAN 1
ROLL OFF
DUMP TRAILERS
LOW BED TRAILER
DELIVERIES: HIGH DECK TRAILERS
WELDING TRUCK 1
FUEL TRUCK 1
PICKUP TRUCKS 1
LIGHT TOWERS 13
DELAYS: T-74 D WN AT 7:30 PM, AND DRIVER SITE MULE 1
SWITCHED TO 7 7. T-74 WENT TO WHITESTONE DUMP TRUCKS
AND T-27 WAS I OUGHT BACK. 10 WHEEL DUMP TRUCK
T-75 PULLED QI AT 11:55 AND BACK AT 1:10 FLASHING ARROW BOARD 1
T-76 PULLED 01 AT 11:55 AND BACK AT 1:10 OFFICE TRAILER/GENER. 1
CARGO BOXES 4
FLAT TRUCK
PUMP 2
ROLLER
RAINMAKER/GENIE LIFT 1
Description of Wo k:
ANTICIPATED W JRK
CONTINUE REMI )VING DEBRIS FROM LOWER LEVELS OF TOWER 2 AND SOUTH OF MAIN CHILLER PLANT
MAN WATERING STATIONS FOR DUST CONTROL_____________
MAINTAIN TRAFFIC FLOW INTO AND OUT OF AREA
2 MACHINES AT .EVELS B-5, 2 MACHINES AT LEVEL B-6; EL 242
CONTINUE ON B 6 IN MER ROOM & REMOVE ALL PIPING ON B-6
LOADS OUT: 13 J__________________________________________
YUKESOUT: 34