Daily work force report, World Trade Center, Nov 28, 2001

Machine-extracted title · confidence 41%

Day shift workforce and equipment counts for World Trade Center, Nov 28, 2001.

NYC-WTC_000279727
Page image
Page image not rendered yet.
The pipeline renders page images incrementally; check back or read the OCR text alongside.
OCR text

OCR status: ok · source: pdftotext

NYC 9/11 Public Portal Document

GRACE CONTRACTING CORP. 151^5 6th Road. Whitestone. N.Y. 11357-(718) 767-9000 DATE: NOVEMBER28, 2001 (DAY) FINAL

DAILY WORK FORCE REPORT

Job Name & Location: World Trade Center Contract No. Weather Conditions

Labor Equipment CLASSIFICATION UANTIT I Description MANNED STANDBY IDLE SUPERINTENDENT 1 CAT 966 LOADER 1 PROJECT ENGINEER 2 CAT446 BACKHOE 1 OFFICE ENGINEER 1 CAT 973 LOADER 1 FOREMEN 1 CAT 365 GRAPPLER 1 SAFETY OFFICER 1 I CAT 375 GRAPPLER 1 LABORERS 21 HITACHI 750 GRAPPLER 1 IRON WORKERS 1 HITACHI 550 GRAPPLER 1 LOCAL 14 4 [HITACHI 550 GRAPPLER 1 LOCAL 15 8 IHITACH11200 grapple'^ 1 CARPENTER 1 185 CFM COMPRESSOR 1 CARPENTER FOREMAN 1 235 HAMMER HOE RAM 1 TEAMSTERS 11 MECHANICS TRUCK 2 MECHANICS 3 TOOL TRUCK 1 HOUSE WRECKERS 6 TOOL VAN 1 ROLL OFF DUMP TRAILERS 7 LOW BED TRAILER DELIVERIES: AWISCO HIGH DECK TRAILERS 3 1. HARDHATS WELDING TRUCK 1 2. HARDHATS FUEL TRUCK 1 3. HARDHATS PICKUP TRUCKS 8 LIGHT TOWERS 9 2.5 HOURS SITE MULE 3 DUMP TRUCKS 10 WHEEL DUMP TRUCK FLASHING ARROW BOARD 1 OFFICE TRAILER/GENER. 1 CARGO BOXES 3 FLAT TRUCK PUMP 2 ROLLER 1 RAINMAKER/GENIE LIFT 1

Description of Work:__________________________________________________________________ I HOUR DELAY OF 235 & 550 TO CORRECT MACHINE OF TULLEYS FRO FALLING IN HOLE AT THE .SOUTH EAST CORNER OF TOWER 2___________________________________________________ LOADS OUT 95_____________________________________________________________________ CONTINUE TO EXTEND ROAD NORTH OF TOWER 2 AND MEET UP WITH AMEC._______________ MANNED TARPING AND TRIMMING STATIONS___________________________________________ MANNED WATER STATIONS FOR DUST CONTROL_______________________________________ MAINTAIN TRAFFIC FLOW IN AND OUT OF AREA_________________________________________ CONTINUE REMOVING DEBRIS FROM LOWER LEVELS OF NORTHWEST CORNER OF TOWER 2 PREP FOR THE BURNING OF THE NORTHWEST CORNER COLUMN BEAMS GRACE CONTIjACTIIirtfc^P Approved By: Title: For: SUPERINTENDENT

CITY_21MC100_004401709

NYC-WTC_000279727

OCR can misread numbers and units. Confirm readings against the page image before using them.

NYC-WTC_000279727Source: NYC Law Department, mirrored locally

Related records

Browse subjects →

Ranked by indexed similarity. Reasons describe shared subjects and filing context; check the source records.

Same-box records

Filed elsewhere

No available related records indexed in this group.

More like this page

Similar subjects in other documents. Similarity does not establish the same event, measurement or conclusion.

Page similarity is temporarily unavailable or this page has no indexed vector.

Others also read

Readers open these alongside this record — through an Ask answer, the same folder, or indexed similarity. Not a claim they are about the same event.

Compare copies and versions →