Daily work force report, World Trade Center, Dec 4 2001

Machine-extracted title · confidence 28%

Night shift daily workforce and equipment at World Trade Center, December 4, 2001.

NYC-WTC_000278688
Page image
Page image not rendered yet.
The pipeline renders page images incrementally; check back or read the OCR text alongside.
OCR text

OCR status: ok · source: pdftotext

NYC 9/11 Public Portal Document

I I GRACE CONTRACTING CORP. 151-45 6th Road. Whitestone. N.Y. 11357-(718) 787-9000 DATE: DECEMBER 4, 2001 (NIGHT FINAL)

DAILY WORK FORCE REPORT

Job Name & Location: World Trade Center Contract No. Weather Conditions i

Labor irI Equipment , CLASSIFICATiCiN I Description MANNED STANDBY DLE SUPERINTENDENT 2 CAT 966 LOADER 1 PROJECT ENGINEER 1 CAT 446 BACKHOE 1 OFFICE ENGINEER CAT 973 LOADER 1 FOREMEN 1 CAT 365 GRAPPLER 1 SAFETY OFFICER CAT 375 GRAPPLER 1 LABORERS 18 HITACHI 750 GRAPPLER 1 IRON WORKERS HITACHI 550 GRAPPLER 1 LOCAL 14 5 HITACHI 550 GRAPPLER 1 LOCAL 15 8 HITACHI 1200 GRAPPLER : 1 CARPENTER 185CFM COMPRESSOR 1 CARPENTER FOREMAN 235 HAMMER HOE RAM 1 TEAMSTERS 11 MECHANICS TRUCK 1 1 MECHANICS 2 TOOL TRUCK 1 HOUSE WRECKERS 10 TOOL VAN ROLLOFF DUMP TRAILERS 7 LOW BED TRAILER HIGH DECK TRAILERS 3 WELDING TRUCK FUEL TRUCK 1 NOTE: REMOVAL OF DEBRIS HAMPERED ENTIRE SHIFT BY PICKUP TRUCKS 2 ACTIVITIES AT CHILLER F’LANT LIGHT TOWERS 13 SITE MULE 3 DUMP TRUCKS 10 WHEEL DUMP TRUCK FLASHING ARROW BOARD 1 OFFICE TRAILER/GENER. 1 CARGO BOXES 3 FLAT TRUCK PUMP 2 1 ROLLER RAINMAKER/GENIE LIFT 1 u Description of Work: LOADS OUT: 2________________________________________ LOAD OUT STEEL AND DEBRIS MAN TARPING AND TRIMMING STATIONS ______________________________________________________________ MAN WATER STATIONS FOR DUST CONTROL____________________________________________________________ 'maintain traffic flow IN AND OUT OF AREA CONTINUE REMOVING DEBRIS FROM LOWERl^ELS OF NW CORNER OF TOWER 2 TO MEET AMEC'S ROADWAY CONTINUE BURNING OF THE WEST WALL COLUMN BEAMS ELEVATIONS: ALL MACHINES LEVEL E-5 253

GRACE CONTRACTING CORP Approved By: Title: For: BY: A SUPERINTENDENT

DAILY WORK FORCE REPORT 1204N.xls

CITY_21MC100_004752868

NYC-WTC_000278688

OCR can misread numbers and units. Confirm readings against the page image before using them.

NYC-WTC_000278688Source: NYC Law Department, mirrored locally

Related records

Browse subjects →

Ranked by indexed similarity. Reasons describe shared subjects and filing context; check the source records.

Same-box records

Filed elsewhere

No available related records indexed in this group.

More like this page

Similar subjects in other documents. Similarity does not establish the same event, measurement or conclusion.

Others also read

Readers open these alongside this record — through an Ask answer, the same folder, or indexed similarity. Not a claim they are about the same event.

Compare copies and versions →