Daily workforce report, World Trade site, Dec 2001

Machine-extracted title · confidence 38%

Daily work force listing and equipment for World Trade site on Dec 28, 2001.

NYC-WTC_000269223
Page image
Page image not rendered yet.
The pipeline renders page images incrementally; check back or read the OCR text alongside.
OCR text

OCR status: ok · source: pdftotext

NYC 9/11 Public Portal Document

GRACE CONTRACTING CORP. 15ms 6th Road. Whitastona, N.Y. 11357-(718)767-6000 DATE: TUESDAY 12/28/01 DAY (FINAL)

DAILY WORK FORCE REPORT

Job Name & Location: World Trade Center Contract No. Weather Conditions

Labor Equipment CLASSIFICATION QUANT. Description MANNED STANDBY IDLE SUPERINTENDENT 1 CAT 966 LOADER 1 PROJECT ENGINEER 1 CAT 446 BACKHOE 1 OFFICE ENGINEER CAT 973 LOADER 1 FOREMEN CAT 365 GRAPPLER 1 SAFETY OFFICER 1 CAT 375 GRAPPLER I—1 LABORERS 21 CAT 375 GRAPPLER 1 zi IRON WORKERS 1 HITACHI 750 GRAPPLER 1 LOCAL 14 6 HITACHI 550 GRAPPLER 1 LOCAL 15 9 HITACHI 1200 GRAPPLER 1 CARPENTER 1 185 CFM COMPRESSOR 1 CARPENTER FOREMAN 2 235 HAMMER HOE RAM 1 TEAMSTERS 1 MECHANICS TRUCK 2 MECHANICS 2 TOOL TRUCK HOUSE WRECKERS 6 TOOL VAN 1 ROLL OFF DUMP TRAILERS LOW BED TRAILER DELIVERIES: OZONE PARK LUMBER HIGH DECK TRAILERS ■ WELDING TRUCK 1 ■ FUEL TRUCK 1 ■ PICKUP TRUCKS 8 ■ LIGHT TOWERS . 13 ■ SITE MULE 3 ■ DUMP TRUCKS ' 10 WHEEL DUMP TRUCK ■ FLASHING ARROW BOARD 1 750 DOWN AT 10:20 AM- BOOM BROKE IN HALF (4 HRS) ■ OFFICE TRAILER/GENER. 1 375 BECAME MANNED ONCE 750 WENT DOWN (8 HRS) ■ CARGO BOXES 4 ■ FLAT TRUCK 1 ■ PUMP 2 ■ ROLLER 1 ■ RAINMAKER/GENIE LIFT 1

Description of Work:________________________________________________________________________________ COMPLETED WORK___________________________________________________________________ MAINTAINED TRAFFIC FLOW INTO AND OUT OF AREA________________________________________________ CONTINUED REMOVING DEBRIS FROM LOWER LEVELS OF TOWER 2 AND SOUTH OF MAIN CHILLER PLANT MANNED WATERING STATIONS FOR DUST CONTROL________________________________________________ LEVELS B-5, EL 253_______________________________________________________________________________ LOADS OUT: 104 VUKESOUT: 227

GRACE CONTRACTING CQ Approved By: Title: BY: For: SUPERINTENDENT

DAILY WORK FORCE REPORT1228D.xls

CITY_21MC100_005019613

NYC-WTC_000269223

OCR can misread numbers and units. Confirm readings against the page image before using them.

NYC-WTC_000269223Source: NYC Law Department, mirrored locally

Related records

Browse subjects →

Ranked by indexed similarity. Reasons describe shared subjects and filing context; check the source records.

Same-box records

Filed elsewhere

No available related records indexed in this group.

More like this page

Similar subjects in other documents. Similarity does not establish the same event, measurement or conclusion.

Others also read

Readers open these alongside this record — through an Ask answer, the same folder, or indexed similarity. Not a claim they are about the same event.

NYC-WTC_000290106

Final daily workforce report for World Trade site, Dec 19 2001.

Similar indexed content

Compare copies and versions →