Tri' -..6' ■ ',V - GRACE CONTRACTING CORP. isiiseih 03d, Whitestone, N.Y. 11357-(718) 767-9000 DATE; JANUARY 5, 2002 DAY (FINAL)
DAILY WORK FORCE REPORT
Job Nan e & Location: Worjd Trade Center Contract No. Weather Conditions
Labor I Equipment CLASSIFICATION QUANT. I Description MANNED STANDBY IDLE Superintendent 2 CAT 966 LOADER 1 Ik ENGINEER 2 CAT 446 BACKHOE . 1 [OFFICE ENGINEER CAT 973 LOADER 1 N 1 CAT 365 GRAPPLER 1 ||SAFETY|OFFICER CAT 375 BUCKET 1 s__ 19 CAT 375 GRAPPLER HITACHI 750 GRAPPLER 1 RKERS 1 [LOCAL 14 7 HITACHI 550 BUCKET 1 LOCAL -<5 10 HITACH11200 GRAPPLER 1 CARPENTER 185 CFM COMPRESSOR 1 CARPENTER FOREMAN 1 235 HAMMER HOE RAM 1 TEAMSTERS_________ 1 MECHANICS TRUCK 2 MECHAlIllCS 2 TOOL TRUCK HOUSE [WRECKERS 4 TOOL VAN 1 I ROLL OFF DUMP TRAILERS LOW BED TRAILER DELIVERIES; HIGH DECK TRAILERS i — WELDING TRUCK 1 X FUEL TRUCK 1 t PICKUP TRUCKS 8 LIGHT TOWERS 13 SITE MULE 3 DUMP TRUCKS 10 WHEEL DUMP TRUCK FLASHING ARROW BOARD 1 OFFICE TFiAILER/GENER. 1 CARGO BOXES 4 FLAT TRUCK 1 PUMP 2 ROLLER 1 RAINMAKER/GENIE LIFT 1
Description of Work:_____________________________________________________________________________ COMPLETED WORK________________ ___________________________________________________________ CONTINUED REMOVING DEBRIS FROM LOWER LEVELS OF TOWER 2 AND SOUTH OF MAIN CHILLER PLANT MANNED WATERING STATIONS FOR DUST CONTROL_______________________________________________ MAINTAINED TRAFFIC FLOW INTO AND OUT OF AREA______________________________________________ 2 MACHINES AT LEVELS B-5. 2 MACHINES AT LEVEL B-6; EL 242
LOADS OUT: 52 YUKESOUT: 240
GRACE CONTRACTING CORP| Approved By; BY: Title: For; SUPERINTENDENT
DAILY WORK FORCE REPORT 0105D.xls
CITY_21MC100_003519636
NYC-WTC_000268603
OCR can misread numbers and units. Confirm readings against the page image before using them.
Ranked by indexed similarity. Reasons describe shared subjects and filing context; check the source records.
NYC-WTC_000279965
Day shift workforce and equipment allocation for World Trade Center construction.
2 shared non-person entities · 1 shared topics · similarity 0.972
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000269206
Night preliminary daily workforce report with personnel and equipment at World Trade.
2 shared non-person entities · 1 shared topics · similarity 0.971
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000305549
Tuesday final daily workforce report for World Trade site, listing crews and equipment.
2 shared non-person entities · 1 shared topics · similarity 0.971
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000302461
Day final daily workforce and equipment for World Trade site, Dec 22, 2001.
2 shared non-person entities · 1 shared topics · similarity 0.970
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000388413
Daily labor and equipment list for World Trade site, Jan 2002.
2 shared non-person entities · 1 shared topics · similarity 0.969
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000361548
Night final daily workforce and equipment for World Trade Center site, Dec 5, 2001.
2 shared non-person entities · 1 shared topics · similarity 0.969
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000388412
Day final daily workforce report for World Trade site; equipment and personnel recorded.
2 shared non-person entities · 1 shared topics · similarity 0.969
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000278686
Night shift workforce and equipment counts for World Trade Center, December 5, 2001.
2 shared non-person entities · 1 shared topics · similarity 0.969
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000305533
Day preliminary daily workforce report detailing crews and equipment at World Trade site.
2 shared non-person entities · 1 shared topics · similarity 0.968
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000237597
A daily report from Grace Contracting Corp. detailing the workforce and equipment deployed at the World Trade Center site on December 11, 2001.
2 shared non-person entities · 1 shared topics · similarity 0.968
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000268636
Daily labor and equipment counts for World Trade Center site work.
1 shared non-person entities · 1 shared topics · similarity 0.968
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000388370
Night shift daily workforce and equipment at World Trade site, Dec 5, 2001.
2 shared non-person entities · 1 shared topics · similarity 0.968
machine-extracted · confidence unavailable · Check page ↗No available related records indexed in this group.
Similar subjects in other documents. Similarity does not establish the same event, measurement or conclusion.
NYC-WTC_000279965
Day shift workforce and equipment allocation for World Trade Center construction.
Similarity score 0.986 (not a probability)
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000269206
Night preliminary daily workforce report with personnel and equipment at World Trade.
Similarity score 0.985 (not a probability)
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000305549
Tuesday final daily workforce report for World Trade site, listing crews and equipment.
Similarity score 0.985 (not a probability)
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000302461
Day final daily workforce and equipment for World Trade site, Dec 22, 2001.
Similarity score 0.985 (not a probability)
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000388413
Daily labor and equipment list for World Trade site, Jan 2002.
Similarity score 0.985 (not a probability)
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000361548
Night final daily workforce and equipment for World Trade Center site, Dec 5, 2001.
Similarity score 0.984 (not a probability)
machine-extracted · confidence unavailable · Check page ↗Readers open these alongside this record — through an Ask answer, the same folder, or indexed similarity. Not a claim they are about the same event.
NYC-WTC_000279965
Day shift workforce and equipment allocation for World Trade Center construction.
Similar indexed content
NYC-WTC_000269206
Night preliminary daily workforce report with personnel and equipment at World Trade.
Similar indexed content
NYC-WTC_000305549
Tuesday final daily workforce report for World Trade site, listing crews and equipment.
Similar indexed content
NYC-WTC_000302461
Day final daily workforce and equipment for World Trade site, Dec 22, 2001.
Similar indexed content
NYC-WTC_000388413
Daily labor and equipment list for World Trade site, Jan 2002.
Similar indexed content