NYC-WTC_000322147
Night final daily workforce and equipment roster for World Trade Center site, December 11, 2001.
2 shared non-person entities · 1 shared topics · similarity 0.984
machine-extracted · confidence unavailable · Check page ↗Nightly work force report listing crews and equipment for World Trade Center, Dec 11, 2001.
NYC-WTC_000267222OCR status: ok · source: pdftotext
NYC 9/11 Public Portal Document
GRACE CONTRACTING CORP. ISMS 6lh Road, Whitestone. NY 11357.(718)767-9000 DATE DECEMBER 11, 2001 (NIGHT FINAL) ____________ 8PM DAILY WORK FORCE REPORT
Job Name & Location: World Trade Center Contract No. j Weather Conditions CLEAR & MILD
Labor Equipment CLASSIFICATION QUANT. Description MANNED STANDBY Idle! SUPERINTENDENT 2 CAT 966 LOADER 1 PROJECT ENGINEER 1 CAT 446 BACKHOE 1 OFFICE ENGINEER CAT 973 LOADER 1 FOREMEN 2 CAT 365 GRAPPLER 1 SAFETY OFFICER CAT 375 GRAPPLER 1 LABORERS 17 HITACHI 750 GRAPPLER 1 IRON WORKERS HITACHI 550 GRAPPLER 1 LOCAL 14 5 HITACHI 550 GRAPPLER 1 LOCAL 15 7 HITACH11200 GRAPPLER 1 CARPENTER 185 CFM COMPRESSOR 1 CARPENTER FOREMAN 235 HAMMER HOE RAM 1 TEAMSTERS ZT/ MECHANICS TRUCK 1 1 MECHANICS 1 TOOL TRUCK 1 HOUSE WRECKERS 12 TOOL VAN ROLL OFF DUMP TRAILERS PROVIDED TRUCKING FOR ALL CONTRACTORS ON SITE LOW BED TRAILER TULLY HAD SOME FLATS AND EUKES j HIGH DECK TRAILERS WELDING TRUCK 1200/750/375 DOWN BELOW LOADINGOUT DEBRIS FUEL TRUCK 1 AND STEEL - LOADED OUR TRAILERS AND TULLYS PICKUP TRUCKS 3 TRAILERS AND EUKES ; LIGHT TOWERS 13 SITE MULE 3 550 ON TOP LOADING OUR TRUCKS | DUMP TRUCKS WORKED IN PIPE CHAMBER NORTH OF NORTH 10 WHEEL DUMP TRUCK ROJECTION PLACED MATS AND MILLINGS FLASHING ARROW BOARD 1 USED 446 OFFICE TRAILER/GENER 1 CARGO BOXES 3 DELAYS FLAT TRUCK 1 1200 DOWN FROM 11.45 TO 1.15 - RECOVERY PUMP 2 375 DOWN FROM 10 00 TO 10 30 - RECOVERY ROLLER 1 RAINMAKER/GENIE LIFT 1
Description of Work WORK COMPLETED LOAD OUT STEEL AND DEBRIS j________ 35 GRACE AREA MAN TARPING AND TRIMMING STATIONS 34 EUKES MAN WATER STATIONS FOR DUST CQNTROL 31 FLATS - DOWNSTAIRS MAINTAIN TRAFFIC FLOW IN AND OUT OF AREA 105 AMEC AREA CONTINUE REMOVING DEBRIS FROM LOWER LEVELS OF NW CORNER OF TOWER 2 INSTALLATION OF GPS SYSTEMS ELEVATIONS- ALL MACHINES LEVEL B-5 253
GRACE CONTRACTING CORP Approved By Title “BY: For SUPERINTENDENT T
DAILY WORK FORCE REPORT..!21 IN xIs
CITY_21MC100_0 04579915
NYC-WTC_000267222
OCR can misread numbers and units. Confirm readings against the page image before using them.
Ranked by indexed similarity. Reasons describe shared subjects and filing context; check the source records.
NYC-WTC_000322147
Night final daily workforce and equipment roster for World Trade Center site, December 11, 2001.
2 shared non-person entities · 1 shared topics · similarity 0.984
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000305047
Final daily workforce and equipment listing for World Trade Center site, December 2001.
2 shared non-person entities · 1 shared topics · similarity 0.984
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000388453
Daily workforce listing for World Trade Center project, December 11, 2001.
1 shared non-person entities · 1 shared topics · similarity 0.983
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000356576
Day shift daily workforce and equipment roster for Grace Contracting at World Trade Center site, January 2002.
1 shared non-person entities · 1 shared topics · similarity 0.983
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000429395
Day shift daily workforce and equipment details for World Trade site on 1/19/02.
1 shared non-person entities · 1 shared topics · similarity 0.983
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000305509
Day FINAL daily workforce and equipment for World Trade Center site, February 2002.
1 shared non-person entities · 1 shared topics · similarity 0.982
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000429727
Night final daily workforce and equipment at World Trade Center, Dec 11, 2001.
2 shared non-person entities · 1 shared topics · similarity 0.982
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000305388
Labor and equipment counts for World Trade Center project site on December 11, 2001.
2 shared non-person entities · 1 shared topics · similarity 0.982
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000305495
Day final daily workforce and equipment listing for World Trade Center site.
1 shared non-person entities · 1 shared topics · similarity 0.982
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000305184
Daily workforce and equipment details for World Trade, Jan 29, 2002.
1 shared non-person entities · 1 shared topics · similarity 0.981
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000361470
Night final daily workforce report for World Trade Center site on Dec 11, 2001.
2 shared non-person entities · 1 shared topics · similarity 0.981
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000429460
Night shift daily workforce and equipment at World Trade Center site.
1 shared non-person entities · 1 shared topics · similarity 0.981
machine-extracted · confidence unavailable · Check page ↗No available related records indexed in this group.
Similar subjects in other documents. Similarity does not establish the same event, measurement or conclusion.
NYC-WTC_000322147
Night final daily workforce and equipment roster for World Trade Center site, December 11, 2001.
Similarity score 0.992 (not a probability)
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000305047
Final daily workforce and equipment listing for World Trade Center site, December 2001.
Similarity score 0.992 (not a probability)
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000388453
Daily workforce listing for World Trade Center project, December 11, 2001.
Similarity score 0.992 (not a probability)
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000356576
Day shift daily workforce and equipment roster for Grace Contracting at World Trade Center site, January 2002.
Similarity score 0.992 (not a probability)
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000429395
Day shift daily workforce and equipment details for World Trade site on 1/19/02.
Similarity score 0.991 (not a probability)
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000305509
Day FINAL daily workforce and equipment for World Trade Center site, February 2002.
Similarity score 0.991 (not a probability)
machine-extracted · confidence unavailable · Check page ↗Readers open these alongside this record — through an Ask answer, the same folder, or indexed similarity. Not a claim they are about the same event.
NYC-WTC_000322147
Night final daily workforce and equipment roster for World Trade Center site, December 11, 2001.
Similar indexed content
NYC-WTC_000305047
Final daily workforce and equipment listing for World Trade Center site, December 2001.
Similar indexed content
NYC-WTC_000388453
Daily workforce listing for World Trade Center project, December 11, 2001.
Similar indexed content
NYC-WTC_000356576
Day shift daily workforce and equipment roster for Grace Contracting at World Trade Center site, January 2002.
Similar indexed content
NYC-WTC_000429395
Day shift daily workforce and equipment details for World Trade site on 1/19/02.
Similar indexed content