FEDERAL EMERGENCY MANAGEMENT AGENCY O M B. No. 3067-0151
PROJECT WORKSHEET Expires April 30, 2001
PAPERWORK BURDEN DISCLOSURE NOTICE
Public reporting burden for this form is estimated to average 30 minutes. The burden estimate includes the time for reviewing
instructions, searching existing data sources, gathenng and maintaining the needed data, and completing and submitting the forms]
You are not required to respond to this collection of information unless a valid 0MB control number is displayed in the upper nght
corner of tne forms. Send comments regarding the accuracy of the burden estimate and any suggestions for reducing the burden to
Information Collection Management, Federal Emergency Management Agency, 500 C Street. SW, Washington. DC 20472,
Paperwork Reduction Project (3067-0151) NOTE Do not send your completed form to this address. I
DECLARATION NO PROJECT NO FIPS NO DATE CATEGORY
FEMA- 1391 -DR- NY 061-51000-33 12/19/01 E
0/KMAGE FACILITY WORK COMPLETE AS OF
Ventilation Cleaning and Repair 09/21/01 100 %
Af’PLtCANT COUNTY
New York City Housing Preservation and Development New York
LOCATION LATITUDE LONGITUDE
100 Gold Street, New York. NY 10038
DAMAGE DESCRIPTION AND DIMENSIONS
The collapse of the World Trade Center (WTC) on September 11, 2001 caused a massive cloud of pulverized concrete and dust to
imoact neighboring buildings, blocks away from the World Trade Center complex. The building of New York City's, Housing
Preservation and Development (HPD) is located at 100 Gold Street, approximately four blocks away.
The dust cloud from the collapse of the WTC directly impacted the building at 100 Gold Street and covered the building with a layer
of pulverized debris Debris and the possible shock wave of the collapse damaged an air intake fan on top of the building. In
addition, dust and pulverized debris that settled on the roof of the building clogged the external filters and louvers, thereby creating
significant ventilation problems Dust and pulvenzed debris entered the fan chamber and insulation The ventilation system
carried this dust and pulvenzed debris throughout the building. The lobby of 100 Gold Street was also used as a relief center to
provide equipment, food, shelter, change of clothes, and supplies for displaced citizens and rescue personnel working at the WTC
site The dust and debris that impacted 100 Gold Street and brought in by displaced citizens and rescue personnel was possibly
contaminated with asbestos
SCOPE OF WORK
Work complete consists of abatement and restoration of the ventilation system on the basis of design, capacity, and function of
such systems as existed prior to the disaster and in conformity with applicable standards. This work was conducted by several
contractors with spec alizations in ventilation systems, air quality restoration, and air sampling, monitoring, and analytical testing.
A memorandum from R. Radhakrshnen. P E from the City of New York, Department of Environmental Protection, dated Septembei
14. 2001, gave guidance to building owners on procedures for clean-up of asbestos containing materials (see attached document)
This memorandum and the U S. Environmental Protection Agency (EPA) - National Emission Standard for Hazardous Air
Pollutants (NESHAP) 40 CFR subpart M, part 61 were used as a basis for the necessary procedures to be performed at all public
facilities.
Degmor, Inc provided labor, material, and equipment to perform surface de-contamination and air quality restoration of the air
handling chamber in the basement, lobby, each floor, and the roof. AAF International provided labor, filters, and matenals needed
for repairing and cleaning the air intake fan on top of the building. Consulting & Testing Services. Inc. (CTSl) performed air
monitoring, testing, and analysis, in accordance to NESHAP, for each floor as pari of the building air quality evaluation and dunng
abatement process
Total costs of contractual services for this project total $83,564 70 Costs for contractual service provided by Degmor, Inc total
$57 650 Labor, air chamber filters and material provided by AAF International total $15,639.70 Costs incurred from quality
control air sampling performed by CTSl total $10,275 00. Costs associated with the indoor air quality testing and assessment
($1,500.00), covered under the CTSl contract, are ineligible in accordance with FEMA's current Public Assistance Program.
Documentation to support these costs are in "Back Up. Do Not Scan".
See Narrative for additional information\
Ooes the Scope of Work change the pre-disaster condition at site?
Special Consideration 'ssues included? Yes □ No
□ cs No
Hazard Mitigation proposal included? [ | Yes | X | No
is there insurance coverage on facility? Yes □ No
PROJECT COST
ITEM CODE NARRATIVE QUANTITY/UNIT UNIT PRICE COST
9025 Contract • Degmor Inc.____________________ 1 / LS $ 57,650.00 $ 57,650.00
2 9025 Contract • Consulting & Testing Services, Inc. 1 / LS $ 10.275.00 $ 10,275.00
3' 9025 Contract - AAF International / LS $ 15,639.70 $ 15,639.70
Total $ 83,564.70
PREPARED BY Dan Martin REMARKS Project Officer
FEMA Form 90-91 SEP 98