Daily work force report, World Trade, Jan 27, 2002

Machine-extracted title · confidence 41%

Day shift daily workforce and equipment at World Trade site, Jan 27, 2002.

NYC-WTC_000263641
Page image
Page image not rendered yet.
The pipeline renders page images incrementally; check back or read the OCR text alongside.
OCR text

OCR status: ok · source: pdftotext

NYC 9/11 Public Portal Document

GRACE CONTRACTING CORP. 161-45 eih Road, Whitestone, N.Y. 11357-(718) 767-9000 DATE; 1/27/02 DAY FINAL

DAILY WORK FORCE REPORT

Job Name & Location: World Trade Center Contract No. Weather Conditions

Labor Equipment CLASSIFICATION QUANT. Description MANNED STANDBY IDLE SUPERINTENDENT CAT 966 LOADER 1 PROJECT ENGINEER 1 CAT 446 BACKHOE 1 OFFICE ENGINEER CAT 973 LOADER 1 FOREMEN 1 CAT 365 GRAPPLER 1 SAFETY OFFICER CAT 375 GRAPPLER 2 iLABORERS______________________________ 9 HITACHI 750 GRAPPLER 1 IRON WORKERS HITACHI 550 GRAPPLER ~ iLOCAL 14_______________________________ 5 IHITACHI 550 GRAPPLER LOCAL 15 5 HITACH11200 GRAPPLER~ 1 CARPENTER 1 [185 CFM COMPRESSOR 1 CARPENTER FOREMAN 1 235 HAMMER HOE RAM ~ 1 TEAMSTERS (FUEL) 1 MECHANICS TRUCK 2 TEAMSTERS (FLATBEDS, DUMPS, AND EUKES) 14 TOOL TRUCK MECHANICS 2 TOOL VAN 1 'house WRECKERS ROLL OFF DUMP TRAILERS LOW BED TRAILER HIGH DECK TRAILERS DELIVERIES; WELDING TRUCK 1 FUEL TRUCK 1 PICKUP TRUCKS 5 LIGHT TOWERS 5 SITE MULE 3 DUMP TRUCKS 10 WHEEL DUMP TRUCK FLASHING ARROW BOARD 1 OFFICE TRAILER/GENER. 1 CARGO BOXES 3 FLAT TRUCK PUMP 2

Description of Work:

CONTINUE REMOVING DEBRIS FROM LOWER LEVELS OF TOWER 2_____________________________________ MAINTAIN TRAFFIC FLOW INTO AND OUT OF AREA OF TOWERS_______________________________________ SPOT FOR MACHINES IN TOWERS________________________________________________________________ EXCAVATE TOWER 1 TO B 6 FOR BRIDGE EVCAVATE NORTH OF TOWER 1 TO ACCOMMODATE NEW ROAD FOR TIE BACKS. EXCAVATE EAST OF MER ROOM FOR NEW ROAD________________________________________ LOADS OUT 108_____________________________________________________________ ________________ YUKELOADS 153_________________________________________________________ DOT LOADS 81 GRACE CONTRACTING CORP Approved By: BY: Title: For; SUPERINTENDENT

DAILY WORK FORCE REPORT0127D.xls

CONFIDENTIAL, CITY_21MC100_013119670 SUBJECT TO PROTECTIVE ORDER NO. 2, SEPT. 2008

NYC-WTC_000263641

OCR can misread numbers and units. Confirm readings against the page image before using them.

NYC-WTC_000263641Source: NYC Law Department, mirrored locally

Related records

Browse subjects →

Ranked by indexed similarity. Reasons describe shared subjects and filing context; check the source records.

Same-box records

Filed elsewhere

No available related records indexed in this group.

More like this page

Similar subjects in other documents. Similarity does not establish the same event, measurement or conclusion.

Others also read

Readers open these alongside this record — through an Ask answer, the same folder, or indexed similarity. Not a claim they are about the same event.

NYC-WTC_000237645

Night shift report from Grace Contracting documenting labor and equipment counts at the World Trade Center site on January 10, 2002.

Similar indexed content

Compare copies and versions →