NYC 9/11 Public Portal Document
GRACE CONTRACTING CORP.
151456th Road, wnitastona, N.Y. 11367-(718)767-9000 DATE: 1/15/02 NIGHT FINAL
DAILY WORK FORCE REPORT
lob Name & Location: World Trade Center
:ontract No.
Veather Conditions: UNSEASONABLY MILD, YET BLUSTERY (3S mph WIND) & COLD. MOSTLY DARK.
Labor Equipment
CLASSIFICATION QUANT. Description MANNED STANDBY IDLE
ISUPERINTENDENT 2 CAT 966 LOADER 1
PROJECT ENGINEER 1 CAT 446 BACKHOE
OFFICE ENGINEER____________________ CAT 973 LOADER________ 1
FOREMEN 2 CAT 365 GRAPPLER 1
SAFETY OFFICER ________________ CAT 375 GRAPPLER 1
LABORERS g CAT 375 BUCKET 1
IRON WORKERS HITACHI 750 GRAPPLER 1
LOCAL 14___________________________ 5 HITACHI 550 GRAPPLER
LOCAL 15 7 HITACHI 1200 GRAPPLER 1
CARPENTER 185 CFM COMPRESSOR 7
CARPENTER FOREMAN 235 HAMMER HOE RAM 1
TEAMSTERS (FUEL) 1 MECHANICS TRUCK 1 1
MECHANICS 1 TOOLTRUCK
HOUSE WRECKERS 3 TOOLVAN
TEAMSTERS (STEEL AND DEBRIS: EUKES) 14 ROLL OFF
DUMP TRAILERS
LOW BED TRAILER
DELIVERIES: HIGH DECK TRAILERS
WELDING TRUCK
FUEL TRUCK 1
PICKUP TRUCKS 3
LIGHT TOWERS 5
SITE MULE 3
DUMP TRUCKS
10 WHEEL DUMP TRUCK
FLASHING ARROW BOARD 1
DELAYS: LOST 3.5 HOURS DUE TO FDNY ACTIVITY OFFICE TRAILER/GENER. 1
IN THE HOLE. GRAPPLES DID NOT LOAD IN THE CARGO BOXES 3
HOLE. FLAT TRUCK 1
PUMP 2
RAINMAKER/GENIE LIFT 1
Description of Work:
COMPLETED WORK____________________________________________________________
CONTINUED REMOVING DEBRIS FROM LOWER LEVELS______________________________
MANNED WATERING STATIONS FOR DUST CONTROL________________________________
MAINTAINED TRAFFIC INTO AND OUT OF AREA____________________________________
APPROXIMATELY 3.5 HOUR DELAY DUE TO FDNY ACTIVITY RELATED TO FIRE IN THE HOLE.
LOADS OUT: 83
EUKESOUT: 138
GRACE CONTRACTING CORP „
Approved By:
Title:
For: SUPERINTENDENT ZX r.
DAILY WORK FORCE REPORT0115N.xls
CONFIDENTIAL, CITY_21MC100_013119543
SUBJECT TO PROTECTIVE ORDER NO. 2, SEPT. 2008
NYC-WTC_000263618
OCR can misread numbers and units. Confirm readings against the page image before using them.