Daily work force report, World Trade Center, Jan 2002

Machine-extracted title · confidence 34%

Daily workforce and equipment list for World Trade Center site, Jan 2002.

NYC-WTC_000263605
Page image
Page image not rendered yet.
The pipeline renders page images incrementally; check back or read the OCR text alongside.
OCR text

OCR status: ok · source: pdftotext

NYC 9/11 Public Portal Document

GRACE CONTRACTING CORP. 151-»5et(lRoad, Whitestone. N.Y. 11357-(718) 767-9000 DATE: 1-9-02 DAY FINAL

DAILY WORK FORCE REPORT

Job Name & Location: World Trade Center Contract No. Weather Conditions

Labor ZZZZ jIL Equipment CLASSIFICATION QUANT. IfI Description MANNED STANDBY IDLE SUPERINTENDENT |CAT 966 LOADER 1 PROJECT ENGINEER 2 (CAT 446 BACKHOE 1 OFFICE ENGINEER CAT 973 LOADER 1 FOREMEN 1 CAT 365 GRAPPLER 1 SAFETY OFFICER CAT 375 BUCKET 1 LABORERS 20 CAT 375 GRAPPLER 1 IRON WORKERS HITACHI 750 GRAPPLER 1 LOCAL 14 6 HITACHI 550 BUCKET 1 LOCAL 15 9 HITACHI 1200 GRAPPLER 1 CARPENTER 165 CFM COMPRESSOR 1 CARPENTER FOREMAN 1 235 HAMMER HOE RAM 1 TEAMSTERS 1 MECHANICS TRUCK 2 MECHANICS 2 TOOL TRUCK HOUSE WRECKERS 6 TOOL VAN 1 ROLL OFF DUMP TRAILERS LOW BED TRAILER DELIVERIES: HIGH DECK TRAILERS WELDING TRUCK 1 FUEL TRUCK 1 PICKUP TRUCKS 5 LIGHT TOWERS 15 SITE MULE 3 ■

DUMP TRUCKS 10 WHEEL DUMP TRUCK ‘LIGHT TOWERS USED FOR 2 HOURS DURING DAY FLASHING ARROW BOARD 1 OFFICE TRAILER/GENER. 1 CARGO BOXES 4 FLAT TRUCK 1 PUMP 2 RAINMAKER/GENIE LIFT 1

... .................... ............ - Description of Work:__________________________________________________________________________ " l'~ COMPLETED WORK_________________________________________________________________________ CONTINUE REMOVING DEBRIS FROM LOWER LEVELS OF TOWER 2 AND SOUTH OF MAIN CHILLER PLANT MAINTAIN TRAFFIC FLOW INTO AND OUT OF AREA MAN WATERING STATIONS FOR DUST CONTROL________________________________________________ LOADS OUT: 106___________________________________________________________________________ EUKESOUT: 192

GRACE CONTRACTING CO^Eih Approved By:

For: SUPERINTENDENT

DAILY WORK FORCE REPORT0109D.xls

CONFIDENTIAL, CITY_21MC100_013119530

SUBJECT TO PROTECTIVE ORDER NO. 2, SEPT. 2008

NYC-WTC_000263605

OCR can misread numbers and units. Confirm readings against the page image before using them.

NYC-WTC_000263605Source: NYC Law Department, mirrored locally

Related records

Browse subjects →

Ranked by indexed similarity. Reasons describe shared subjects and filing context; check the source records.

Same-box records

Filed elsewhere

No available related records indexed in this group.

More like this page

Similar subjects in other documents. Similarity does not establish the same event, measurement or conclusion.

Others also read

Readers open these alongside this record — through an Ask answer, the same folder, or indexed similarity. Not a claim they are about the same event.

NYC-WTC_000237641

Day shift report from Grace Contracting documenting labor and equipment counts at the World Trade Center site on January 8, 2002.

Similar indexed content

NYC-WTC_000237643

Day shift report from Grace Contracting documenting labor and equipment counts at the World Trade Center site on January 9, 2002.