GRACE CONTRACTING CORP.
,51-45 6th Road. Whitestone, N.Y. 1,357-(718)767-9000 DATE; 2/11/02 DAY FINAL
DAILY WORK FORCE REPORT
Job Name & Location: World Trade Center
Contract No.
Weather Conditions
Labor I Equipment
CLASSIFICATION QUANT. I Description MANNED STANDBY IDLE
SUPERINTENDENT 2 |CAT 966 LOADER 1
FOREMEN 1 |CAT 365 GRAPPLER 1
PROJECT ENGINEER 2 CAT 375 BUCKET 1
SAFETY OFFICER 1 CAT 375 GRAPPLER 1
LABORERS 14 HITACHI 750 GRAPPLER 1
IRON WORKERS HITACHI 1200 GRAPPLER 1
LOCAL 14 4 185 CFM COMPRESSOR *SEE NOTE
LOCAL 15 5 235 HAMMER HOE RAM 1
CARPENTER MECHANICS TRUCK 1 1
CARPENTER FOREMAN 1 TOOLTRUCK 1
TEAMSTERS (FUEL) 1 TOOLVAN
MECHANICS 3 ROLL OFF
HOUSE WRECKERS DUMP TRAILERS
LOW BED TRAILER
HIGH DECK TRAILERS
DELIVERIES: WELDING TRUCK 1
FUEL TRUCK 1
PICKUP TRUCKS 5
NOTE; 1S5 CFM COMPRESSOR RUNNING UNMANNED LIGHT TOWERS 5
SITE MULE 3
14 TEAMSTERS (10 DUMP TRAILERS, 4 EUKES ) DUMP TRUCKS
10 WHEEL DUMP TRUCK
375 WENT DOWN 1 PM , THE 1200 REPLACED IT FOR FLASHING ARROW BOARD 1
THE BALANCE OF THE DAY OFFICE TRAILER/GENER. 1
CARGO BOXES 3
FLAT TRUCK
PUMP 2
Description of Work;
___________________________ II
CONTINUE REMOVING DEBRIS FROM LOWER LEVELS OF WTC COMPLEX
[MAINTAIN TRAFFIC FLOW INTO AND OUT OF AREA___________________
CONTINUE LOGGING TRUCKS AND NUMBER OF LOADS OUT OF SITE
LOADS OUT 91__________________________________________________
EUKE LOADS 149
GRACE CONTRACTING CORP
Approved By:
Title:
For:
1
BY:
SUPERINTENDENT
DAILY WORK FORCE REPORT0211D.xls
CONFIDENTIAL, SUBJECT TO PROTECTIVE ORIIJERBOlQ1®E^3Sa5S50
NYC-WTC_000237701