Costs resulting from OMB's displacement from 75 Park Place
Improvements to Leasehold at 59 Maiden Lane ($000's)
Restoration of DoITT CityNet Hub
and 0MB Print Room at 59 Maiden Lane $ 2,017
On Call Services including electrical, security,
and constnjction 123
Relocation Planning & Design, including
Disaster Recovery 711
Subtotal $ 2,851
Equipment Purchases for 59 Maiden Lane
A/S 400 179
Network 420
Servers 135
PC's 683
Printers 1,233
Software 132 IS
Subtotal $ 2,782
Cost of Relocating to 75 Park Place
Environmental Testing $
HVAC 149*^51
Cleaning
PC Disposition, Relocation, & Installation
200/
Security System Replacement
Painting 95 vX a*'
Print Room Structural Analysis & Modification
Cabling, Minor Repairs, Floor Plans
Completion Unfinished DCAS Work*
Replace Entry Doors
Replace Pantry Appliances*
Construction Management
N/A” <
190-1
, 5'z
Subtotal* $ '57
Equipment Purchases for 75 Park Place
DR - Servers $ 71
DR - Software 4
DR - A/S 400 251
Additional PC's/Laptops 114
Network 527
Internet Connectivity 300
UPS/PDU /150
Document Management '^50
Access Control System 150
Training __ 60
Subtotal $ 1,777 ■
Total* $ 8,378
—Estimated DoITT Build-out 59 Maiden Lane 14th Floor $ 2,000
Estimated Law Dept. Relocation 100 Church St. 1,000 <1
Grand Total* $ 11,378
* Cost estimate for construction not available as of 3/1/02