DRAFT Statement of Work
I asiM
3^1^
?HERE
i
SI------ 1
PURPOSE:
The purpose of this contract is to implement indoor sampling to collect settled and airborne dust
samples for analysis to determine concentrations of 7 Chemicals Of Potential Concern (COPC):
dioxin, lead, PAHs, ceramic fibers, fibrous glass, asbestos, and silica. Sampling will be conducted
in 14 hl lildinnsj^own tr)|j^febe affected by the airborne dusts and plume which emanated from
"Ground Zero". Building locations will be selected by the New York City Department of Health.
The contractor shall provide professional technical and field support sen/ices to the U.S.
Environmental Protection Agency (EPA) under the provisions of the contract Statement of Work
(SOW) and other applicable support functions, including equipment and supply purchases,
maintenance and repair of equipment, as well as health & safety and environmental
compliance activities outlined in this SOW- The contractor shall provide all trained personnel,
materials and equipment to perform sampling/monitoring activities as described below or in
Technical Direction Forms (TDFs) issued at any time during the duration of this contract.
STATEMENT OF WORK:
TASK 1: Task Order Management:
Sampling team management shall meet with the PO and other designated EPA representatives
on an as needed basis, at agreed-upon times, to update EPA on the status of tasks and
schedules for their completion and to address relevant administrative and technical issues.
The contractor shall submit all deliverables required under this contract through a cover letter
identifying each document submitted. The contractor shall also maintain a copy of each
deliverable and all field documentation submitted under this contract for 365 days.
The contractor shall review all deliverables prior to submission to EPA. The reviewer shall not have
been significantly involved in the direct preparation of the deliverable being reviewed. The
review shall assure that each deliverable is accurate and complete, technically sound, and free
of clerical errors.
All contractor personnel performing field activities as per this contract shall have current OSHA
basic 40 hour certification. The contractor shall implement a health and safety program in
accordance with its Health and Safety Plan and all applicable Federal, state, and local laws
and regulations and EPA site specific work rules. The contractor shall revise its Health and Safety
plan as needed to assure that all requirements specified above are addressed.
Deliverables
Any environmental data collected for the agency must comply with EPA Order 5360.1 CHG 2, Policy and
Program Requirements for the Mandatory Agency -wide Quality System. This document provides the
requirements for the conduct of quality management practices, including Quality Assurance (QA) and
Quality Control (QC) activities, for all environmental data collection and environmental technology
programs performed by or for this Agency.