AMBASSADOR CONSTRUCTION CO, INC.
MINUTES OF CONSULTANT ’S MEETING #15
PROJECT: Mayor’s Office of Emergency Management
7 World Trade Center -1, 7 & 23rd Floors
Amb. Job#S57-5175
DATE: October 27, 1998
PRESENT: Martin Schneider Ambassador
Jack Klein Ambassador
M. Mathew DCAS
Glenn Pymento DCAS
Joseph Domingvez DCAS
Bob Melaniff DITT
Juan Mejia Swanke Hayden Connell
John Hughes OEM
Fernando Alvarez Vikonics
Michael Pisano Vikonics
Bob Hudson Motorola
Steve Harte Motorola
Philip Moy Motorola
1. PWJECT STATUS
1st Floor: - Chopping solution for steel interference provided. Ambassador to coordinate.
(3^
----- ---- - Steel delivery 10/28/98. Sc
7th Floor: - Steel is set for emergency generator and water storage tank.,
- Duct removal and reinstallation this weekend.
- Drywall work at corridor walls to be completed this week. ----- —
- Generator to be delivered 11/7/98.
'----- Ambassador to coordinate water storage tank work.
23rd Floor.- Painter to start 11/9/98.
- Raised floor to start 11/11/98.
- Cooling tower dunnage to be complete by 11/7/98 44.-*
- Cooling towers to be delivered 11/7/98.
- Brandt FJ\/ enclosures to be released. Delivery week of 11/9/98.—.
- Ace requested completion of A/V room.—
- Acme Partition - Need delivery date.— y
Roof: - Steel to be delivered end of next week.
Y'
- Metal panel wall to be delivered the week of 11/9/98.
GJENERAL
- Ambassador advised that Novalink will ship 11/5/98.
Continued. ..