SEP 04 ’98 14=23 PR AMBASSADOR CONSTR. C0212 949 9762 TO 6694107 P.02/03
AMBASSADOR CONSTRUCTION CO, INC.
♦
PROJECT:
MINUTES OF CONSULTANT’S MEETING #7
Mayor's Office of Emergency Management
7 World Trade Center
1, 7 & 23rd Floors
Amb. Job#S57-5175
DATE: September 1, 1998
PRESENT: Walter Weems Silverstein Properties
Martin Schneider Ambassador
Jack Klein Ambassador
Jay Koven Ambassador
Glenn Pymento DCAS
M. Matthew DCAS
Bob Melaniff DITT
Bob Hudson Motorola
Juan Mejia Swanke Hayden Connell
Joe Aliotta Swanke Hayden Connell
John Hughes OEM
David Litvin OEM
Bill Hanley Shem Milsom & Wilke
1. SHOP DRAWING STATUS
- Critical shop drawings out for review:
Zuntabelle fixture
Steel shop drawings
2500 amp panel
Duct Drawing A-7-1
2. PRQJE,CT STATUS
- Ambassador advised that substantial completion of the 23rd Floor may be delayed
due to the hurricane wall.
- Ambassador advised of the following:
Layout and framing is 90% complete.
Drywall installation is approximately 40% complete.
Sprinkler mains and branches are 70% complete.
Plumbing drainage work on the 22nd Floor is 70% complete.—
Black iron i;; approximately 35% complete.
Blind pockets are approximately 40% complete.
Electrical roughing on 23rd Floor is 60% complete.
Riser core work is 78% complete.
Riser work is 30% complete.
7th Floor demolition is complete.
Chopping for core work completed on 9/2/98.
i
Core work to start this week.
Continued...