G. Sheetrock finish;
1) Where the sheetrock meets the turrets, material is jaggered and poor
workmanship, locations; M 1, 2, 7, 17, 19, 21.
2) Metal turret over M 7 needs to be cleaned.
H. Metal Ceiling Tiles:
1) There are numerous tiles in need of realignment. There are tiles that need
to be replaced due damage ( dents). All tiles were identified by Juan
Mejia on construction drawings.
2) Installation of audio speaker in the area of seat number 64 vibrates when
used, ( speaker installation shims are visible).
I. Wood Paneling:
1) Damaged pieces :
Behind glass door to watch command in three places, (damage occurred
prior to installation of door stop and door closer, Mazen was notified to
install).
2) Panel damaged to left of M 10.
3) Numerous areas have glue on finish of paneling.
4) Remove wood shim to right of M 11.
J. Hurricane doors :
1) Access to doors behind wood panels not possible.
2) Metal clips loose or missing.
3) Wood panels were installed as normal, no change to make
it possible to remove.
K. Electrical;
1) Damaged light fixture :
ceiling wall fixture to the right of M 13 has an opening of 2”.
2) Complete inspection of electrical systems.
4