Copies and versions
← Back to recordCopies are not independent tests. A high similarity score can also match a reused form; it does not establish which copy came first or whether their findings agree.
- Construction cost breakdown, 7 World Trade Center, 1998 · Box 7DCAS
NYC-WTC_000173425
· similarity 0.984 (not a probability)machine-extracted · confidence unavailable · Check page ↗ - Project cost summary, Mayor's OEM renovation, Sept 1998 · Box 7DCAS
NYC-WTC_000173312
· similarity 0.981 (not a probability)machine-extracted · confidence unavailable · Check page ↗ - Construction budget summary, 7 World Trade Center, 1998 · Box 7DCAS
NYC-WTC_000173423
· similarity 0.977 (not a probability)machine-extracted · confidence unavailable · Check page ↗ - Construction budget summary, 7 World Trade Center, 1998 · Box 7DCAS
NYC-WTC_000173424
· similarity 0.970 (not a probability)machine-extracted · confidence unavailable · Check page ↗
Selected filing
Revised budget with contingencies, 7 World Trade Center, 1998NYC-WTC_000173426
Budget sheet showing total costs including furniture, moving contingencies, and LAN/computer expenses for the Mayor's OEM project.
Citywide Administrative Services, Dept. of · Volume NYC-WTC0007 · Box 7DCAS
Open the record for the City’s folder metadata.

Comparison filing
Construction budget summary, 7 World Trade Center, 1998NYC-WTC_000173423
Financial sheet detailing bid prices, scope deductions, and revised costs for hurricane wall and bulletproof materials at the site.
Citywide Administrative Services, Dept. of · Volume NYC-WTC0007 · Box 7DCAS
Open the record for the City’s folder metadata.
