Selected filing

Price Revision Memo for OEM Construction Project, July 1998

NYC-WTC_000172998

Memorandum detailing a cost increase of $117,684 due to design substitution for the Mayor's Office of Emergency Management construction project.

Citywide Administrative Services, Dept. of · Volume NYC-WTC0007 · Box 7DCAS

Open the record for the City’s folder metadata.

Selected filing: NYC-WTC_000172998, page 1

Comparison filing

Cost estimate and change orders for hurricane wall, July-August 1998

NYC-WTC_000172996

Sheet detailing cost estimates and change orders for the hurricane wall construction at the Mayor's Office of Emergency Management.

Citywide Administrative Services, Dept. of · Volume NYC-WTC0007 · Box 7DCAS

Open the record for the City’s folder metadata.

Comparison filing: NYC-WTC_000172996, page 1