Forest City Tech Place Associates L.P
1 Metro Tech Center North
Brooklyn, NY 11201
Re: Redesign fee for UPS
FDNY Dispatch Center
11 Metro Tech Center, 4"' Floor
Brooklyn, NY
Dear Mr. Sanna:
We write with reference to the change orders submitted by SHCA and Kling Linguist and
forwarded to this office on 6/9/1999, for the redesign of the UPS system.
The change orders have been reviewed and the submitted costs have been found reasonable.
Therefore, in view of the foregoing, a total amount of $62,690.00 is hereby approved, subject to
audit, as A&E fees for the redesign of the UPS system.
The following is a breakdown of the project’s budget:
Construction budget for 4"’ floor $ 8,285,036.00
Amount approved for 4“’ floor construction on 6/7/99 $ 6,798,750.00
Amount approved for UPS system on 6/29/99 $ 711,116.00
Amount approved by Work Order on 7/8/99 $ 5,250.00
Amount approved by this CO for additional A&E fees $ 62,690.00
Total amount approved for the project $ 7,577,806.00
Balance remaining in the budget $ 707,230.00