JAN 21 ’99 0g:32 PR AMBASSADOR CONSTR. C0212 949 9762 TO 6693640 P.02/02
AMBASSADOR CONSTRUCTION CO.? INC
0
January 20,1999
Mr. Walter Weems
Silverstein Properties, Inc.
7 World Trade Center
New York, NY 10048
RE; Mayor’s Office of Emergency Management
7 World Trade Center -1,7 & 23rd Floors
Change Order #56
Amb. Job #557-5175
Dear Mr. Weems:
We are pleased to submit herewith our change order #056 to perform the following work at the above
referenced premises for the sum of NINETEEN THOUSAND TWO HUNDRED FORTY TWO DOLLARS
($19,242.00);
SCOPE OF WORK
As per Cosentini'5 memo dated 1/18/99, install (1) double duplex Nema S-20R outlet on fiber rack
located at column 42 on First Floor. Run 2 #4 and 1 #8 ground in 1" conduit from panel ELP-76 to
double duplex outlet on fiber rack. Coring and patching are included in this cost
Electrical Cost $14,600.00
Patching (allow) 2,000.00
Subtotal $16,600.00
General Conditions 1,328.00
Overhead & Fee 1,076.00
Insurance 238,00
Total $19,242.00
"^3
Please notify us if we are to proceed with this work.
/
Veryiruly yours,
AMBASSADOR CONSTRUCTION CO., INC.
Martin Schneider
Vice President
MS:as
cc; Juan Mejia - SHC
Glenn Pymento - DCAS
Accepted:__________ Dated;
c:\wpdoc8\oem\ee9loemcoS6.wjM5)
317 MADISON AVENUE, NEW YORK, NY 10017, 212 922 1020, FAX 212 949 9762
** TOTAL PAGE.02 **
NYC-WTC_000172220