NYC 9/11 Public Portal Document
OEM PROJECT COSTS
MAYOR'S OFFICE OF EMERGENCY MANAGEMENT
7 WORLD TRADE CENTER____________________
NEW YORK
Accounting of the Project's Budget
Project Budget Ambassador's
CO cost proposals
Original budget of the project $14,287,986
Amount reduced from budget BBlil
Amount available for construction work $13,727,986
Construction amount approved on 6/2/98 $12,864,619
Amount approved by CO # 1 on 7/8/98 $117,684
Amount approved by CO # 2 on 8/11/98________ $7
Total amount approved for construction to date $12,989,303
Amount to be approved for CO # 3 $3,704
Amount to be approved for CO # 4 Bulletin #1:
Port authority Comments -$2,950
Audio Visual work & equipments -$289,803
Hurricane wall
(a) Construction $331310
(b) Motorized dampers $135,906
Additional amount to be approved for CO # 3&4 $178,167
Projected total cost of construction $13,167,470
Projected balance available in the budget $560,516
Note: In addition to the above, there are two additional change orders for which Ambassador has not submitted pricing.
1. Request from OEM to include Blast proof doors at the entrance with Master window- expected cost approx. $25,000.00
2. Relocating miscellaneous ductwork, electric and fiber optic cables on 7th floor (Generator room) expected cost approx. $75,000.00
The projected balance available in the budget will be reduced by this amount. Also, there could be additional costs/change orders
resulting from site conditions etc.
NYC-WTC_000172053