AMBASSADOR COwirRUCTlON CQ. INC.
November 18,1998
Mr. Walter Weems
Silverstein Properties, Inc.
7 Worid Trade Center
New York, NY 10048
RE; Mayors Office of Emergency Management
7 World Trade Center -1,7 & 23rd Floors
Change Order #031
Amb. Job # 8.57-317$
Dear Mr. Weems:
We are pleased to submit herewith our change order #031 to perform the following work at the
above referenced premises for the sum of FIFTY FOUR THOUSAND THREE HUNDRED FIFTY
FOUR ($54,354.00):
Furnish and install the security wire in conduits as per Vikonics spec #11020-0
- Labor
- Vikonics Equipment
- Miscellaneous Material 150.001 .
Subtotal
General Conditions
Overhead and Fee 37939:6©'
Insurance
Total
Please issue to us a change order for this work so we may proceed.
We trust the above meets with your approval and we look forward to the continued pleasure of
serving you.
If you have any questions, please do not hesitate to contact us.
Very truly yours,
^MBASSAipR CONSTRUCTION CO,, INC.
Martin Schneider
Vice President
M5:am
cc: Juan Mejia - SHC
Glenn Pymento - DCAS
Dated