AMBASSADOR CONSTRUCTION CO.. INC. si*
♦
Mr. Walter Weems
Silverstein Properties Inc.
7 World Trade Center
December 23, 1998
New York, NY 10048
Re: Mayor’s Office of Emergency Management
7 World Trade Center
Change Order #043
Amb. Job#S57-5175
Dear Mr. Weems:
We are pleased to submit herewith our change order #043 to perform the following work at the
above referenced premises for the sum of ELEVEN THOUSAND SEVEN HUNDRED FIFTY
NINE DOLLARS ($11,759.00).
In accordance with the letter from John Hughes of the Office of Emergency Management
dated 12/22/98, for the RG-6U plenum cable for the Time Warner T.V..
The following is the cost:
Material $3,250.00
Labor 4,895.00
Ceiling Patch ___^QDJ3.0Q
Subtotal ! $10,145.00
General Conditions 812.00
Overhead and Fee 657.00
Insurance __14fLQQ
TotakyP 756
We trust the above meets with your approval and we look forward to the continued
pleasure of serving you.
If you have any questions, please do not hesitate to contact us.
Very truly yours.
^AMBASSADOR CO^TRUCTION CO., INC.
Martin Schneider
Vice President
cc: Glenn Pymento/DCAS
Juan Mejia/SHC
MS:am
Accepted:____________ Dated:
C <OPFICEWVPWIN«VPOOC$«EMV:0-S\OEMC043WPO
317 MADISON AVENUE, NEW YORK. NY 10017, 212 922 1020, FAX 212 949 9762
NYC-WTC_000171860