AMBASSADOR CONSTRUCTION CO., INC.
April 27. 1999
Mr. Walter Weems
Silverstein Properties, Inc.
7 World Trade Center
New York, NY 10048
RE: Mayor’s Office of Emergency Management
7 World Trade Center -1, 7 & 23rd Floors
Change Order #084
Amb. Job #^S5Z-5175
Dear Mr. Weems:
We are pleased to submit herewith our credit change order #084 to perform the
following work at the above referenced premises for the sum of THIRTY
THOUSAND SIX HUNDRED EIGHTY ONE DOLLARS <$30,681.00>:
This work included:
- Credit for elimination of 8 T.V. monitors and
installation of same. Credit includes restocking charge. <$27,540.00>
- Credit for installation of wall wash fixture in reception area. <$270.00>
- Add for labor and material to remove and reinstall
cove light in the EOC room so that steel for monitors
could be installed. Monitors were elimiinated at a
later date. ___ $1,341.00
Subtotal <$26.469.00> 3 4
General Conditions <$2,118.00> "
Overhead & Profit y<1,715.00>
Insurance / <379.0Q> I
Total ^^$30,681.00> i