Copies and versions
← Back to recordCopies are not independent tests. A high similarity score can also match a reused form; it does not establish which copy came first or whether their findings agree.
- Change order review correspondence, 7 World Trade Center, Aug 1999 · Box 7DCAS
NYC-WTC_000168379
· similarity 0.998 (not a probability)machine-extracted · confidence unavailable · Check page ↗ - Change Order #88 approval memo, 7 World Trade Center, June · Box 7DCAS
NYC-WTC_000171737
· similarity 0.975 (not a probability)machine-extracted · confidence unavailable · Check page ↗ - DCA letter negotiating change orders #35-71 at 7 WTC, Nov · Box 7DCAS
NYC-WTC_000171352
· similarity 0.974 (not a probability)machine-extracted · confidence unavailable · Check page ↗ - Approval of multiple change orders, 7 WTC, Feb-Mar 1999 · Box 7DCAS
NYC-WTC_000168471
· similarity 0.974 (not a probability)machine-extracted · confidence unavailable · Check page ↗
Selected filing
DCAS letter on negotiated change orders #73-95, Nov 1999NYC-WTC_000171646
Letter from DCAS confirming review and cost negotiation for ten change orders submitted by a contractor for the Mayor's Office of Emergency Management.
Citywide Administrative Services, Dept. of · Volume NYC-WTC0007 · Box 7DCAS
Open the record for the City’s folder metadata.

Comparison filing
Change Order #88 approval memo, 7 World Trade Center, JuneNYC-WTC_000171737
Memo approving a negotiated cost of $130,000 for fuel oil line supply and installation at the Mayor's Office of Emergency Management.
Citywide Administrative Services, Dept. of · Volume NYC-WTC0007 · Box 7DCAS
Open the record for the City’s folder metadata.