Date: November 22, 1999
TO: Christopher Lane
Office of Engineering Audit
From: Richard Ramos /
Executive Space Design/ DRES
Re: Mayor’s Office of Emergency Management
7 World 14ade Center
New York, NY
1
CP#37836
CAPIS ID#PW3261346
Contract# 98F2654
Enclosed please find the 5'*’ invoice dated September 29,1999 received from Silverstein Properties for
the construction rent payments. As of this date, this office has approved a total amount of
$14,103,659,00 for the construction of the project. (Letter attached). Please process payment as soon
as possible.
Construction cost budget $14,287,986.00
Less landlord’s contribution $ 1,668,858.00
Maximum amount chargeable to City of New York $12,619,128.00
Total construction cost approved as of November 22 ,1999 $14,103,659.00
Less landlord’s contribution $ 1,668,858.00
Amount chargeable to City of New York $12,434,801.00
Prior approved payments $11,384,322.00
Amount approved by this payment $ 300,000.00
Total amount approved $11,684,322.00
Amount retained for signoffs $ 400,000.00
Amount retained for punch list & work not completed $ 350,479.00
Total money retained $ 750,479.00
Balance remaining in the budget $ 184,327.00
If we can be of any further assistance, please do not hesitate to call me at 669-80'86 or Glenn
Pymento at 669-8094.
c: Jeff Kondrat Mangalathil Mathew
Glenn Pymento Josep Dominqvez
Vinicius Castagnola Joseph Menasce
c./ni> dou/consibud/oenvpaynicnkS/inin
NYC-WTC_000171596
OCR can misread numbers and units. Confirm readings against the page image before using them.