Same-box records
Change order proposal for OEM hatch door switch, March 2001 · Box 7DCASNYC-WTC_000171477
Proposal from Ambassador Construction to install a disconnect switch for a hatch door release at the Mayor's Office of Emergency Management for $762.
4 shared non-person entities · 1 shared topics · Same agency, volume and box · similarity 0.982
Revised Change Order #10 receiver, 7 WTC, Sep 1998 · Box 7DCASNYC-WTC_000168661
Revised Change Order #10 submitted for the installation of a special class I package receiver at 7 World Trade Center dated September 16, 1998.
3 shared non-person entities · 1 shared topics · Same agency, volume and box · similarity 0.971
Change Order #95, 7 World Trade Center receptacles, August 1999 · Box 7DCASNYC-WTC_000172349
Cover letter submitting Change Order #95 for $1,046 to install three new electrical receptacles in the Mayor's conference room at 7 World Trade Center.
3 shared non-person entities · 1 shared topics · Same agency, volume and box · similarity 0.963
Change order #111 submission memo, Feb 2000 · Box 7DCASNYC-WTC_000168341
Letter submitting change order #111 for insulation, painting, and hardware work at the Mayor's Office of Emergency Management facility.
3 shared non-person entities · 1 shared topics · Same agency, volume and box · similarity 0.963
Change Order #99 Submission, 7 World Trade Center, Oct 1999 · Box 7DCASNYC-WTC_000168375
Contractor submission for Change Order #99 to install separate electrical circuits in executive and coffee areas.
3 shared non-person entities · 1 shared topics · Same agency, volume and box · similarity 0.962
Change order #001 for OEM Inergen reserve system, Dec 2000 · Box 7DCASNYC-WTC_000171488
Submission of change order #001 by Ambassador Construction to install a connected reserve Inergen supply system at the Mayor's Office of Emergency Management.
4 shared non-person entities · 1 shared topics · Same agency, volume and box · similarity 0.961
Change Order #95 Submission, 7 World Trade Center, Aug 1999 · Box 7DCASNYC-WTC_000168388
Letter submitting change order #95 to install three new electrical receptacles under a conference room table for $1,046.
3 shared non-person entities · 1 shared topics · Same agency, volume and box · similarity 0.961
Fire-rated hatch installation work order, 7 WTC, Jun 2000 · Box 7DCASNYC-WTC_000171500
Letter transmitting change order #113 for $3,253 to remove and install new fire-rated hatch at 7 World Trade Center tank room.
2 shared non-person entities · 1 shared topics · Same agency, volume and box · similarity 0.961
Change Order #61, 7 World Trade Center, Jan 1999 · Box 7DCASNYC-WTC_000171408
Contractor submission for change order covering wiring installation for auxiliary contacts within existing relays.
3 shared non-person entities · 1 shared topics · Same agency, volume and box · similarity 0.961
Revised Change Order #10 for package receiver, 7 World Trade · Box 7DCASNYC-WTC_000172008
Letter submits revised change order to furnish and install a special Class I package receiver at the project site.
3 shared non-person entities · 1 shared topics · Same agency, volume and box · similarity 0.960
Change order #79 for blast door plates, 7 WTC, Apr · Box 7DCASNYC-WTC_000171669
Letter submitting Change Order #79 to install reinforcing plates for blast-proof doors at 7 World Trade Center.
2 shared non-person entities · 1 shared topics · Same agency, volume and box · similarity 0.959
Revised Change Order #9 for wood door modifications, 7 World · Box 7DCASNYC-WTC_000172006
Letter submits revised change order for mahogany door and jamb replacements at the Mayor's Office of Emergency Management.
3 shared non-person entities · 1 shared topics · Same agency, volume and box · similarity 0.959