NYC Law Department release
Independent mirror · updated as the City releases more · v1.2.6
← Document results/7DCAS/7 World Trade Center Mayor's Office of Emergency Management -1st, 7th, & 23rd Floors Change Order #40
Document / 1 page

Change Order #40, 7 World Trade Center, Dec 1998

Machine-extracted title · confidence 100%

Memo submitting Change Order #40 for welding new rebar into trench at the Mayor's Office of Emergency Management in 7 World Trade Center.

NYC-WTC_000168575

Folder label: “7 World Trade Center Mayor's Office of Emergency Management -1st, 7th, & 23rd Floors Change Order #40

Page image
Scanned page image, NYC-WTC_000168575
OCR text

OCR status: ok · source: pdftotext

NYC 9/11 Public Portal Document

Silverstein Properties, Inc I /’ World rradr? Contei New York, N Y. 10048 lelephone: ? 12 619-8569 Pax. ?12-732-5190

December 21, 1998

Mr. Glenn Pymento Department of City Wide Administrative Services Division of Real Estate Services 1 Centre Street, DRES - Room 2000 North New York, New York 10007 RE: 7 World Trade Center Mayor's Office of Emergency Management -1" 7*, & 23'“^ Floors Change Order #40_____________ Dear Mr. Pymento:

Attached please find change order #40 in the amount of $26,427.00 submitted by Ambassador Construction for the following scope of work:

As per the engineer's verbal instructions to weld new rebar intrench with 3" over lap at each end. In order to expose the end of the existing rebar the concrete has to be chopped away.

- New rebar and welding $7,800.00 - Chop existing concrete $15,000.00 - Sub-total $22,800.00 - General Conditions $1,824.00 - Overhead and Fee $1,477.00 - Insurance $326.00

Total $26,427.00

*Alternate If welding of rebar has to be performed on $4,080.00 Overtime

If this meets with your approval, please sign and return to my office. Thank you.

Sincerely,

Walter J. '^^ems III Building Manager cc: Cathy Giliberti Chi Chu Bill Dacunto Richard Ramos (DCAS) Josep Domingvez (DCAS)

NYC-WTC_000168575

OCR can misread numbers and units. Confirm readings against the page image before using them.

NYC-WTC_000168575Source: NYC Law Department, mirrored locally

Related records

Browse subjects →

Ranked by indexed similarity. Reasons describe shared subjects and filing context; check the source records.

Same-box records

Change Order #62 memo, 7 WTC, Feb 1999 · Box 7DCAS

NYC-WTC_000168506

Memo submitting Change Order #62 for $9,679 to complete roofing details at a new curb on the 7 World Trade Center roof.

5 shared non-person entities · 1 shared topics · Same agency, volume and box · similarity 0.950

machine-extracted · confidence unavailable · Check page ↗
Change Order #21 transmittal, 7 WTC, Oct 1998 · Box 7DCAS

NYC-WTC_000173818

Letter submitting Change Order #21 for structural work at the water tank and switch gear areas on the 7th floor of 7 World Trade Center.

5 shared non-person entities · 1 shared topics · Same agency, volume and box · similarity 0.947

machine-extracted · confidence unavailable · Check page ↗

Filed elsewhere

No available related records indexed in this group.

More like this page

Similar subjects in other documents. Similarity does not establish the same event, measurement or conclusion.

Page similarity is temporarily unavailable or this page has no indexed vector.

Others also read

Readers open these alongside this record — through an Ask answer, the same folder, or indexed similarity. Not a claim they are about the same event.

NYC-WTC_000171847 · Box 7DCAS

Letter submitting Change Order #40 for $26,427.00 for unspecified scope of work at the Office of Emergency Management.

Similar indexed content

NYC-WTC_000171881 · Box 7DCAS

Letter submitting Change Order #47 for stainless steel generator flexes to address height restrictions at 7 World Trade Center.

Similar indexed content

NYC-WTC_000168557 · Box 7DCAS

Memo submitting Change Order #47 for furnishing stainless steel flexes for generators at 7 World Trade Center due to height restrictions.

Similar indexed content

Compare copies and versions →