January 26, 1999
Mr. Glenn Pymento
Department of City Wide Administrative Services
Division of Real Estate Services
1 Centre Street, DRES - Room 2000 North
New York, New York 10007
RE: 7 World Trade Center
Mayor's Office of Emergency
Management-V', 7^ & 23'^ Floors
Change Order #59
Dear Mr. Pymento:
Attached please find change order #59 in the amount of $10,948.00 submitted by
Ambassador Construction for the following scope of work:
In accordance with Cosentini Associates' memo dated 1/22/99, furnish and install (1)
duplex separate circuit on rack near column #42 on V‘ floor. The 4" conduit that is being
used for the fiber cable will be used. A new drag line will have to be snaked through the
existing conduit. The access for the 4" conduit will be on the 7* floor.
Electrical Cost $9,445.00
General Conditions $756.00
Overhead and Fee $612.00
Insurance $135.00
Total $10,948.00
If this meets with your approval, please sign and return to my office. Thank you.
Sincerely,
Walter^. Weems III
Building Manager
cc; Cathy Giliberti
Chi Chu
Bill Dacunto
Richard Ramos (DCAS)
Josep Domingvez (DCAS)
NYC-WTC_000168518
OCR can misread numbers and units. Confirm readings against the page image before using them.