Submission of Change Order #53 for $2,898 covering additional electrician work at the site.
4 shared non-person entities · Same agency, volume and box · similarity 0.945
machine-extracted · confidence unavailable · Check page ↗Letter submitting change order #104 for galvanized riser and fiber optic cable installation for telephone and camera systems at 7 World Trade Center.
NYC-WTC_000168367–000168368Folder label: “Mayor's Office of Emergency Management ®7 World Trade Center ®Change Order #104”

OCR status: ok · source: pdftotext
NYC 9/11 Public Portal Document
Silverstein Properties, Inc. 1 7 World Trade Center New York, N.Y. 10048 Telephone: 212-619-6569 Fax: 212-732-5190
November 10,1999
Mr. Glen Pymento Department of Citywide Administrative Services Division of Real Estate Services 1 Centre Street, DRES- Room 2000 North New York, NY 10007
RE: Mayor's Office of Emergency Management 7 World Trade Center Change Order #104 Dear Mr. Pymento:
Attached please find Change Order #104 in the amount of fifty four thousand thirty one dollars ($54,031.00) for the following work:
1. Furnish and install a 2 1/2" galvanized riser from loading dock to telephone frame in the 2"'^ floor. 2. From frame room, furnish and install a 2 1/2" galvanized riser to the 23^'^ floor telephone closet in freight car lobby. 3. 2-24 strand fiber cables from loading dock to frame room, then to the 23'^^ floor Lan room using existing cable tray. Cable is a four week lead time and is plenum rated. 4. Furnish and install IIOV 15A outlet in 2"*^ floor frame room. Power from new 3KVA XFMR to rack on 2"^^ floor. Transformer location in pump room off loading dock.
Electrical cost $45,000.00 Patching $1,500.00 Subtotal $46,500.00 General Conditions $3,720.00 Overhead & Fees $3,013.00 Insurance $798.00 Total $54,031.00
NYC-WTC_000168367
OCR can misread numbers and units. Confirm readings against the page image before using them.
Ranked by indexed similarity. Reasons describe shared subjects and filing context; check the source records.
NYC-WTC_000173994
Submission of Change Order #53 for $2,898 covering additional electrician work at the site.
4 shared non-person entities · Same agency, volume and box · similarity 0.945
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000168692
Contractor submission of Change Order #003 for plug mold outlet and A/V work at the Mayor's Office of Emergency Management.
4 shared non-person entities · 1 shared topics · Same agency, volume and box · similarity 0.943
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000173874
Change order #26 submitted for drywall work including closing door openings at 7 World Trade Center.
4 shared non-person entities · 1 shared topics · Same agency, volume and box · similarity 0.943
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000171352
Letter from DCA to a property firm confirming negotiated costs for Change Orders #35 through #71 at the Mayor's Office of Emergency Management.
1 shared non-person entities · Same agency, volume and box · similarity 0.941
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000168603
Memo submitting Revised Change Order #26R to perform drywall and door closing work at 7 World Trade Center.
4 shared non-person entities · 1 shared topics · Same agency, volume and box · similarity 0.941
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000171808
Letter from DCAS submitting revised change order #26R for work at the Mayor's Office of Emergency Management.
4 shared non-person entities · 1 shared topics · Same agency, volume and box · similarity 0.941
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000171781
Fax cover sheet from DCAS Real Estate Services transmitting documents regarding space design for the Mayor's Office of Emergency Management.
1 shared non-person entities · Same agency, volume and box · similarity 0.941
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000168471
City correspondence reviewing and negotiating costs for numerous submitted change orders related to facility work.
1 shared non-person entities · Same agency, volume and box · similarity 0.941
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000173881
Revised change order #16 submitted for electrical plan revisions regarding drawing changes at 7 World Trade Center.
3 shared non-person entities · Same agency, volume and box · similarity 0.940
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000173944
Cover letter submitting Change Order #67 for furnishing and making up five power cords with 15 amp plugs.
4 shared non-person entities · 1 shared topics · Same agency, volume and box · similarity 0.940
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000171453
Letter dated February 1, 1999, submitting Change Order #66 for furnishing and installing floor boxes at 7 World Trade Center.
4 shared non-person entities · 1 shared topics · Same agency, volume and box · similarity 0.939
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000168607
Contractor submission for change order to close door openings and perform scar patching at 7 World Trade Center.
3 shared non-person entities · 1 shared topics · Same agency, volume and box · similarity 0.939
machine-extracted · confidence unavailable · Check page ↗No available related records indexed in this group.
Similar subjects in other documents. Similarity does not establish the same event, measurement or conclusion.
Page similarity is temporarily unavailable or this page has no indexed vector.
Readers open these alongside this record — through an Ask answer, the same folder, or indexed similarity. Not a claim they are about the same event.
Submission of Change Order #53 for $2,898 covering additional electrician work at the site.
Similar indexed content
Contractor submission of Change Order #003 for plug mold outlet and A/V work at the Mayor's Office of Emergency Management.
Similar indexed content
Change order #26 submitted for drywall work including closing door openings at 7 World Trade Center.
Similar indexed content
NYC-WTC_000171352
Letter from DCA to a property firm confirming negotiated costs for Change Orders #35 through #71 at the Mayor's Office of Emergency Management.
Similar indexed content
Memo submitting Revised Change Order #26R to perform drywall and door closing work at 7 World Trade Center.
Similar indexed content