NYC 9/11 Public Portal Document
THE CITY OF NEW YORK
DEPARTMENT OF CITYWIDE ADMINISTRATIVE SERVICES
DIVISION OF REAL ESTATE SERVICES
Date: February 22, 2000
TO: Christopher Lane
Office of Engineering Audit
Richard Ramos^^^
From:
Executive Director of Space Design/ DRES
Re: Mayor’s Office of Emergency Management
7 World Trade Center
New York, NY
CP#37836
CAPIS ID#PW3261346
Contract# 98F2654
Enclosed please find the 6* invoice dated February 4, 2000 received from Silverstein Properties for the
construction rent payments. As of this date, this office has approved a total amount of $ 14,133,187.00
for the construction of the project. (Letter attached). Please process payment as soon as possible.
Construction cost budget $14,287,986.00
Less landlord’s contribution $ 1.668,858.00
Maximum amount chargeable to City of New York $12,619,128.00
Total construction cost approved as of February 9,2000 $14,133,187.00
Less landlord’s contribution $ 1,668,858.00
Amount chargeable to City of New York $12,464,329.00
Prior approved payments $11,684,322.00
Amount approved by this payment $ 340,007.00
Total amount approved $12,024,329.00
Amount retained for signoffs $ 400,000.00
Amount retained for punch list & work not completed $ 40,000.00
Total money retained $ 440,000.00
Balance remaining in the budget $ 154,799.00
If we can be of any further assistance, please do not hesitate to call me at 669-8086 or Glenn
Pymento at 669-8094.
c: Jeff Kondrat
Glenn Pymento
IS®
Mangalathil Mathew^
Josep Dominqvez
Vinicius CastagnQia Joseph Menasce
c ;/mydoc/constbud/oem/payment6/mm
NYC-WTC_000168334