NYC 9/11 Public Portal Document
AMBASSADOR CONSTRUCTION CO. INC.
MINUTES OF CONSULTANT’S MEETING #2
PROJECT: Mayor’s Office of Emergency Management
7 World Trade Center
1.7, & 23rd Floors
Amb. Job#S57-517S
DATE: July 28, 1998
PRESENT: Martin Schneider Ambassador
Jack Klein Ambassador
Mark Torre Silverstein Properties
Walter Weems Silverstein Properties
Glenn Pymento DCAS
Bob Melaniff DITT
Josep Domingvez DCAS
Juan Mejia Swanke Hayden Connell
1. SHOP DRAWING STATUS
- Reviewed minutes of 7/21/98
- Ambassador advised that the following shop drawings are still being reviewed:
Hollow Metal, Sheetmetal 2nd Quadrant and Plastic Laminate
- Swanke advised that they would push both Hollow Metal and Duct drawings
- Swanke advised Ambassador to submit hardware schedule
2. PROJKCJLSIArUS
- Reviewed minutes of 7/21/98
- Ambassador advised that layout of partitions is continuing and studding of wall is in
progress
- Electrical layout has proceeded
- Ductwork installation has started
- Chopping for MER room has started
- Ambassador advised that distribution for riser piping will start on 8/1/98
- Ambassador advised that the 7th Floor partitions have been laid out, SPI is
reviewing with adjacent tenant
- DITT submitted schedule for voice/data. Ambassador to coordinate, see attached
3. RFJLSIATUS
- Reviewed minutes of 7/21/98
- No new RFI’s
Continued.../